Installation
4. In cases where the front panel seal is critical, use a torque wrench to ensure all
screws are torqued within the specification above.
5. Connect the cables in the specified order, according to the drawing and steps
below.
Caution:
•
The operator panel must be brought to ambient temperature before it is started
up. If condensation forms, ensure that the operator panel is dry before connecting
it to the power outlet.
•
Ensure that the operator panel and the controller system have the same electrical
grounding (reference voltage level), otherwise errors in communication may
occur.
•
Ensure that the voltage and polarity of the power source is correct.
•
Separate high voltage cables from signal and supply cables.
•
Shielded communication cables are recommended.
24V DC
RS232/
RS422/
RS485
24V DC
A
D
Controller
Power
B
Ethernet
C
The image is illustrative only and may differ slightly from the actual panel.
–
Connect cable A.
–
Connect cable B, using 14-20 AWG (2.08–0.52 mm
2
), 180–220 N-cm
torque.
–
Connect cable C.
–
Connect cable D. The recommended cross-section of the cable is 1.5
mm
2
.
6. Carefully remove the protective film over the operator panel display, take care
to avoid static electricity that could damage the panel.
3.2.1
Connections to the Controller
For information about the cables to be used when connecting the operator panel to
the controller, please refer to the help file for the driver in question.
Beijer Electronics, MAEN329
9