24
10.1.5.
Exchange control UV sensor
After 8,000 hours of operation or with UV lamps or AC reactor cleaning
The UV sensor change due to interruption of operations
1. Device power off
2. Shut off the pipeline inlet and outlet
3. Make UC system depressurized
4. UV sensor Unscrew with fork circuits 17
5. Mounting in reverse order,
6. Please note: quartz glass must be free of condensation, O-ring must sit straight sets
7. Check for leaks and fixed screw
8. Calibrate UV monitoring new
UV sensor SUV
Attention
Do not scratch the quartz protective liner
Clean only with soft cloth or kitchen roll
The quartz protective liner must be dry and clean before installation.