Parameterization and commissioning
CXxxxx-M510/B510
55
Version: 1.0
7. In the tree view on the left click on
PLC – Configuration
, then on the
PLC Settings (Target)
tab.
8. Select the Start PLC under Boot Project and click on
Apply
.
9. Start PLC Control and open the PLC project.
10. In the menu bar at the top click on
Online
, and then on
Choose Runtime System
.
11. Select the runtime system from the CX and click on
OK
.
12. In the menu bar at the top click on
Online
, then
Login
.
The PLC project is logged in.
13. In the menu bar at the top click on
Online
, then
Create Boot Project
.
ð
You have successfully loaded the CX configuration. From now on, TwinCAT will start in Run mode and
the PLC project will start automatically.
Next, the master can be added in a new project in the System Manager and can then be used to find
slaves that have already been set up.