6. Remove the transformer compartment cover and make electrical connections. Electrical connections should be made 

inside the transformer compartment. Make electrical connection as follows (Fig. 6):

120VAC 

  277VAC

White - Common 

 

White - Common

Black - 120VAC 

 

Orange - 277VAC

Green - Ground 

 

Green - Ground

Note:

 Cap unused leads to prevent shorting.

7. Replace the compartment cover and secure in place with (1) #6-32 x 1/4” screw.

8. Verify connections are in place, such as lamps, LED, and test button. 

9. Replace the enclosure cover and secure in place with the cover screws.

10. Open the battery door by unscrewing the captive thumb screw.  (Fig. 7)

11. Connect the battery and close the battery door.

12. Secure the battery door in place by retightening the thumb screw.

13. Cut the ceiling tile to correct size, as needed. (Fig. 8)     

Transformer 

Compartment 

Cover

#6 x 1/4”

Screw

Battery 

Door

Battery 

Connector

LED 

Indicator

Test Button

Fig. 6

Fig. 7

Fig. 8

 

10070166 

R

EV 7 - 08/22

3

800-533-3948 www.barronltg.com

CRL Series

Installation Instructions

Summary of Contents for EXITRONIX CRL Series

Page 1: ...r electrical heaters Do not use outdoors Equipment should be mounted in locations and at heights where it will not be readily subjected to tampering by unauthorized personnel The use of accessory equipment not recommended by the manufacturer may cause an unsafe condition Any modification or use of non original components will void the warranty and product liability Do not use this equipment for ot...

Page 2: ...of the T bar Fig 2a b a Additional chains or cabling shall be used for enclosure securement 3 Remove the 4 6 32 x 3 4 flat head screws from cover Fig 3 4 Remove the cover and connect the lanyards to the lanyard hooks found inside the enclosure Fig 4a b 5 Connect flexible conduit to one of the three available conduit knockouts Fig 5 Wing Nuts Ceiling Bracket Fig 1 Fig 2b Fig 2a 6 32 x 3 4 Flat Head...

Page 3: ... 6 32 x 1 4 screw 8 Verify connections are in place such as lamps LED and test button 9 Replace the enclosure cover and secure in place with the cover screws 10 Open the battery door by unscrewing the captive thumb screw Fig 7 11 Connect the battery and close the battery door 12 Secure the battery door in place by retightening the thumb screw 13 Cut the ceiling tile to correct size as needed Fig 8...

Page 4: ...s The unit equipment will automatically switch to battery mode every 6 months for a period of 30 minutes The unit equipment will automatically switch to battery mode every year for a period of 90 minutes LED Indicator The LED indicator of the emergency unit will display a visual signal indicating the status of the unit Refer to Table 1 for units equipped with a tri color LED indicator Test Button ...

Page 5: ...ill automatically switch to battery mode every month for a period of 1 minute The unit equipment will automatically switch to battery mode every year for a period of 90 minutes Numeric Indicator The numeric indicator of the emergency unit will display a visual signal indicating the status of the unit Refer to Table 2 for units equipped with a numeric indicator Test Button Features MANUAL TEST Pres...

Reviews: