INSTALLATION INSTRUCTIONS

10070166 Rev 4 - 04/19

2

Fig. 4a

Fig. 4b

Lanyard Hook

Lanyard

4. Remove cover and connect lanyards to lanyard hooks found 

    inside enclosure. (Fig. 4a, 4b)

5. Connect flexible conduit to one of the three available conduit 

    knockouts. (Fig. 5)

6. Remove transformer compartment cover. Electrical 

    Connections should be made in transformer 

    compartment. Cap unused primary wire to prevent 

    shorting. (Fig. 6)

120V AC

White - Common

Black - 120V

Green - Ground

277V AC

White - Common

Orange - 277V

Green - Ground 

7. Replace compartment cover and secure in place with (1) #6-32 x 1/4” pan head screw.

8. Verify connections are in place such as lamps, led, and test button. 

9. Replace enclosure cover and secure in place with cover screws.

10. Open battery door by unscrewing captive thumb screw. 

11. Connect battery and close battery door. 

12. Secure in place by retightening thumb screw. (Fig. 7)

13. Cut ceiling tile to correct size as needed. (Fig. 8)    

 

Fig. 5

Fig. 6

Fig. 7

Flexible 

Conduit 

transformer 

compartment 

cover

#6 x 1/4” pan 

head screw

Battery 

Door

Battery 

Connector

Led Indicator

Test Button

Fig. 8

CRL SERIES

800.533.3948 • www.barronltg.com 