INSTALLATION OF HEATER PACKAGE

 1. Disconnect all power to unit before installation.

INSTALLATION

 2. Before installation, check unit serial plate to insure

that the heater package model that you intend to
install is listed as a heater package suitable for use
with the unit.

Under no circumstances shall a heater package be
installed in a unit if the model number of the heater
package does not appear on the unit serial plate.

 3. Remove electric heater access panel and control

panel cover, both inner and outer.  See Figure 2.

 4. All heaters are installed with the thermal cutoffs

positioned to the top of the unit.  Install heat strip(s)
through heater access opening.  Position heat strip
support rod in heater support hole 1, 2 or 3 as
indicated in Table 1 and Figure 3.  Secure in place
with 2 sheet metal screws in mounting holes as
indicated in Table 1 and Figure 3.  On heater
packages with 2 heat strips, install 9KW or 10KW
heater first in position closest to the outlet air frame.
See Figures 4E and 4F.

 5. Install heater control base into top of control panel

as shown in Figure 5.  Secure with 4 sheet metal
screws provided.

 6. Plug male 6 pin connector into mating connector

mounted in control panel.  See Figure 5.

 7. Connect red compressor supply lead to L1 of

terminal block.  Connect black compressor supply
lead to L2 of terminal block.  If 3 phase, connect
yellow supply lead to L3 of terminal block.  See
Figure 5 and wiring diagram.

8. Route wires from heater control base up through

raceway in top right corner of control panel to the
heaters.  See Figure 5.

 9. Wire heater package per wiring diagram supplied

with this heater package.  All wires are stamped with
wire numbers that correspond with terminal numbers
on the wiring diagram and stamped numbers on the
heat strip.  Limit switch wires are terminated with
insulated quick connect terminals.  See Figure 4.

10. Attach adhesive wiring diagram directly above unit

wiring diagram on inner control panel cover.

11. Recheck all wiring.  Break out appropriate circuit

breaker tabs on inner control panel cover to allow
trip lever to protrude.  Replace control panel and
heater access panels

12. Resupply power to the unit and check for proper

operation.

13. Remark serial plate with self-adhesive label attached

to the front of this manual.  See Figure 6.

          WARNING

Install only heater packages listed on unit
serial plate.  Hazard of fire or electrical shock.
Failure to install listed heater package could
result in fire, injury or death.

       WARNING

Disconnect all power to unit before installing
heater package. Hazard of electrical shock.
Failure to disconnect power could result in
injury or death.

Summary of Contents for EHWH42-A05

Page 1: ...B09 EHWH04 A05 EHWA05 B15 EHWH04 A10 EHWA05 B18 EHWH04 A15 EHWA05A C09 EHWH04 A20 EHWA05A C15 EHWH04 B18 EHWA60 A05 EHWH05 B09 EHWA60 B09 EHWH05 B15 EHW05A B18 EHWH05A C09 EHW05H B18 EHWH05A C15 EHW60...

Page 2: ...rix 4 Table 1C Heater Usage by Model Matrix 4 Table 1D Heater Usage by Model Matrix 5 Table 1E Heater Usage by Model Matrix 6 Table 1F Heater Usage by Model Matrix 6 Table 2 Electrical Data and BTU Ou...

Page 3: ...KW A AIR CONDITIONER H HEAT PUMP C AIR CONDITIONER and HEAT PUMP SUITABLE FOR USE IN SEE TABLES 1A 1F ELECTRICAL VERSION A 240 208V 1Ph B 240 208V 3Ph C 460V 3PH TABLE 1A R 22 HEATER USAGE BY MODEL M...

Page 4: ...B WA701 B WA701HB WA721 B WH421 B WH421DB WH421LB WH483 B WH483DB WH483LB WH602 B WH602DB WH602LB TABLE 1C R 22 HEATER USAGE BY MODEL MATRIX V 4 1 4 V 0 6 4 e s a h P 3 9 0 C A 5 0 A W H E X X X X X X...

Page 5: ...A W H E X 4 0 A 4 0 H W H E X X 5 0 A 4 0 H W H E X X 0 1 A 4 0 H W H E X X X 5 1 A 4 0 H W H E X 0 2 A 4 0 H W H E X X 5 0 A 2 4 H W H E X X X X 0 1 A 2 4 H W H E X X X X 5 1 A 2 4 H W H E X X 5 0 A...

Page 6: ...X X X V 4 1 4 V 0 6 4 e s a h P 3 9 0 C A 5 0 A W H E X X X X X X X X X X X 5 1 C A 5 0 A W H E X X X X 4 1 F A 5 0 A W H E X X X X 9 0 C A 5 0 H W H E X X X X X X X X 5 1 C A 5 0 H W H E X X X X X 6...

Page 7: ...3 1 0 3 4 1 6 0 0 1 6 4 9 0 C A 5 0 A W H E 0 8 4 3 9 0 0 7 0 3 5 1 C A 5 0 A W H E 0 8 4 3 5 1 0 0 0 7 4 5 0 A 0 6 A W H E 8 0 2 0 4 2 1 5 5 7 3 5 6 0 7 1 0 0 8 2 1 9 0 B 0 6 A W H E 8 0 2 0 4 2 3 9...

Page 8: ...ton The heat package must consist of the following 1 Basic heater 2 Electric heat control base and wiring 3 Installation instructions 4 Wiring diagram 2 one to be applied to unit 5 Adhesive label to r...

Page 9: ...Manual 2100 254E Page 9 of 17 FIGURE 1 ELECTRICALCONNECTIONS...

Page 10: ...See Figure 5 7 Connect red compressor supply lead to L1 of terminal block Connect black compressor supply lead to L2 of terminal block If 3 phase connect yellow supply lead to L3 of terminal block See...

Page 11: ...Manual 2100 254E Page 11 of 17 FIGURE 2 INSTALLATION OF HEATER PACKAGE...

Page 12: ...W H E C 4 1 9 5 1 C A 5 0 A W H E E 4 3 1 0 1 5 0 A 2 4 A W H E A 4 1 1 1 0 1 A 2 4 A W H E B 4 1 2 1 5 1 A 2 4 A W H E D 4 3 1 3 1 5 0 A 0 6 A W H E A 4 1 4 1 9 0 B 0 6 A W H E C 4 1 5 1 4 0 A 4 0 H...

Page 13: ...Manual 2100 254E Page 13 of 17 FIGURE 3 ROD SUPPORT AND SCREW MOUNTING POSITIONS...

Page 14: ...Manual 2100 254E Page 14 of 17 FIGURES 4A 4D HEATER TERMINAL IDENTIFICATION DRAWINGS FIGURE 4A FIGURE 4C FIGURE 4D FIGURE 4B...

Page 15: ...Manual 2100 254E Page 15 of 17 FIGURES 4E AND 4F HEATER TERMINAL IDENTIFICATION DRAWINGS FIGURE 4E FIGURE 4F...

Page 16: ...Manual 2100 254E Page 16 of 17 FIGURE 5 WIRING DIRECTIONS...

Page 17: ...Manual 2100 254E Page 17 of 17 FIGURE 6 MARKING SERIAL PLATE LABEL...

Reviews: