Roll Up Door Opener Set Up

GDO-6 EasyRoller

®

, RDO-1

Mount the Charger Board

a.  Unplug the drive unit from mains power.

b. Remove the timing cover and light diffuser.

c.  Mount the Charger Board 

 8

 on the chasis and secure with four (4) Taptite ‘P’ M4x8 screws 

16

.

d. Feed the battery harness 

 5

 through the cable clamp 

18

 and secure left corner of the board. Feed the Wire Harness 

 9

 

around the timing assembly, through opening and plug into SBY-03 (4 pin) connector on the control board.

e.  Remove breakaway slot on timing cover and feed wire battery harness 

10

 through slot and replace timing cover. Secure in 

place with screws.

Mount & Connect the Battery

a.  Mount battery backup kit onto support chassis and secure right side screw first (charger board side) 

17

.

b. Position the wire battery harness 

10

 neatly and secure left side of battery kit with cable clamp 

 7

.

WARNING:

 After Step (c) the opener may become active (even when power is off).  

This is a result of a residual charge in the batteries.  

c.  Connect battery harnesses 

 5

 and 

10

 together.

d. Close the timing cover, light diffuser and reconnect power.

NOTE:

 Batteries may take up to 48 hours to charge fully after initial installation.

Re-setup and Test the Opener

a.  Reconnect power and remove the button cover.

b. Press either the OSC button the opener or the programmed transmitter button to test the battery backup installation.

c.  Whilst door is in motion, disconnect mains power. The door should continue to operate as normal.

NOTE:

 Wait for the door to complete its travel.

d. Press either the OSC button on the opener or the progammed transmitter button to activate the door.

e.  Whilst door is in motion, reconnect power and re-install button cover. The door should complete the cycle as normal.

Summary of Contents for V-05

Page 1: ... HARNESS 1 29 TAPTITE SCREW P M3 X 8 4 Sliding Gate Openers Important Safety Instructions WARNING DO NOT short the output of batteries Serious personal injury and or property damage can result from failure to follow this warning During charging and discharging cycles the lead acid batteries may release explosive gases Ensure that the area around the batteries is well ventilated Take care not to al...

Page 2: ... and secure right side screw first charger board side 17 b Position the wire battery harness 10 neatly and secure left side of battery kit with cable clamp 7 WARNING After Step c the opener may become active even when power is off This is a result of a residual charge in the batteries c Connect battery harnesses 5 and 10 together d Close the timing cover light diffuser and reconnect power NOTE Bat...

Page 3: ...in connector on the main control board Mount Connect the Battery a Mount battery pack on side of unit and secure with items 11 and 12 WARNING After Step b the opener may become active even when power is off This is a result of a residual charge in the batteries b Connect battery harnesses 5 and 10 together c Close the cover secure the Light Diffuser with 2 screws and reconnect power NOTE Batteries...

Page 4: ...y Box s nylon gland d Connect the red wire to the Battery Box s terminal and the black wire to the terminal e Feed the other end of the 2 core 18awg gauge cable through the control box s gland f Connect the red wire to the Charger Board s Battery Harness BAT connector and the black wire to the BAT connector Re setup and Test the Opener a Reconnect power b Select Menu 7 on the DCB 05 control board ...

Page 5: ...ing wire 27 through the main cover b Secure the lid to the main cover with screws c Connect battery harnesses 27 and 28 together NOTE Batteries may take up to 48 hours to charge fully after initial installation Re setup and Test the Opener a Reconnect power b Select Menu 7 on the control board press SET select Sub Menu 7 Battery Solar and enable using the OPEN and CLOSE buttons c Setup travel limi...

Page 6: ...finish is travel d Press the transmitter to activate the opener e Whilst the door gate is in motion reconnect power If the door gate stopped or moved very slosly under battery power ensure mains power is connected for 24 48 hours to recharge the batteries Test the opener again under battery power in 72 hours to ensure batteries are working effectively Symptom Possible cause Remedy Door stops or mo...

Page 7: ...tallation configuration or use of the Product contrary to the instructions supplied with the Product g maximum continuous operating time exceeding 1 minute in 10 h the operating force exceeding 15kg 150 Newton when moving the door manually to the open or closed position i door surface area and or weight exceeding 28m2 and 270kg respectively j the door used with the Product not being in safe workin...

Page 8: ...alia Pty Ltd ABN 25 010 473 971 B D Doors 34 36 Marigold St Revesby NSW 2212 P 13 62 63 E enquires bnd com au W www bnd com au August 2015 Automatic Technology Australia Pty Ltd All rights reserved No part of this document may be reproduced without prior permission In an ongoing commitment to product quality we reserve the right to change specification without notice E OE ...

Reviews: