Principles of Operation

During normal operation in the untripped condition, the plug is 

retracted into the fully open position. The downstream pressure 

is monitored by the Overpressure and/or Underpressure sensing 

diaphragms. If an overpressure or underpressure condition 

occurs, the sensing diaphragms will move the trip shaft, causing 

the  valve  to  trip  completely  closed.  After  the  Slam  Shut  has 

tripped, the valve must be reset manually. 

Hydrostatic Testing

All Slam Shut stand alone valves and Slam Shut valves integrated 

into Flowgrid valves are hydrostatically tested at the factory prior 

to  shipment  according  to  ISA-S75.19-1989  and  MSS-SP-61 

standards.
If it is necessary to retest the valve, the Slam Shut valve may 

be hydrotested without any modifications. If a Flowgrid regulator 

is  integrated  into  the  Slam  Shut,  care  should  be  taken  to  not 

damage the diaphragm. Refer to the Flowgrid IOM GEA19583.

Installation

Personal injury, equipment damage, or leakage 

due to explosion of accumulated gas or bursting of 

pressure containing parts, may result if the Slam 

Shut is over pressured, or is installed where service 

conditions could exceed the limits given in the 

specification of this manual, or on the nameplate, or 

where conditions exceed any ratings of the adjacent 

piping or piping connections. Verify the limitations 

of the Flowgrid regulator, Slam Shut valve and pilot 

to ensure none of the devices are over pressured. 

To avoid such injury or damage, provide pressure 

relieving or pressure limiting devices as required by 

applicable codes to prevent service conditions from 

exceeding those limits. Additionally, physical dam-

age to the regulator could result in damage such as 

breaking the pilot (if supplied) off the main valve, 

causing personal injury and/or property damage due 

to explosion of accumulated gas. 
To avoid such injury and damage, install the Slam 

Shut and regulator in a safe location.
Note: The Slam Shut maybe supplied as a stand 

alone unit or integrated into a Flowgrid regulator 

with filters, restrictors and pilots. This procedure 

covers the installation of the Slam Shut and may 

refer to components not ordered with the Slam Shut. 

Consult the proper IOM for the installation of Flow-

grid regulator, filters, restrictors and pilots.

1. 

 Personnel:

 Installation of the Slam Shut valve and/or 

Flowgrid regulator should be made by qualified personnel 

familiar with high pressure piping and pilot operated 

regulators.

2. 

 Prior  Inspection:

 Inspect the Slam Shut valve, regulator, 

pilot, and tubing for any damage that might have occurred in 

shipping. Make sure the body, pilot lines, and inlet piping are 

clear and free from foreign material. 

3.  

Orientation: 

Stand  alone  Slam  Shuts  must  be  installed 

up stream of the pressure regulator to provide secondary 

protection. The Slam Shut valve or Slam Shut integrated 

into a Flowgrid regulator may be installed in any position, 

the best position being one that provides easiest access for 

the Slam Shut, pilot adjustment and maintenance.

4. 

 Screwed End Valves: 

Apply  pipe  compound  to  the  male 

threads starting one or two threads back from the end prior 

to assembling the joint.

5.   

Flanged End Valves: 

Use suitable line gaskets and standard 

bolting practices with flanged bodies. A criss-cross pattern 

of incrementally tightening the line bolts is recommended.

6. 

 Weld End Bodies: 

Before welding a butt weld and/or a socket 

weld  valve  body,  disassemble  the  valve.  On  stand  alone 

Slam Shuts remove the bonnet, Slam Shut body assembly 

and all O-rings. On Slam Shuts integrated into Flowgrid 

valves;  remove  the  Slam  Shut  body  assembly,  Spring 

Case and all trim parts including diaphragm and O-rings. 

Reassemble the valve (refer to the MAINTENANCE section 

of this manual for Disassembly and Assembly procedures) 

and pressurize to check for leaks prior to putting the valve in 

service. 

7. 

 Slam Shut Sense Line: 

Install  a  3/8  inch  OD  tube  from 

the  sense  port  to  a  port  on  the  pipe  line  located  8  to  10 

pipe diameters minimum of straight pipe downstream of 

the final regulator in the run. The sense port is located on 

the downstream side of the controller and latch module just 

above the Slam Shut label.

  

Note: The sense line connection should be away from 

areas of turbulence (such as valves, reducers, and 

elbows) and should have a full opening into the pipe free 

from burrs, drill peels, and weld slag. Shutoff valves are 

not required in the control line(s), but if installed, they 

should be of the full opening type. 

8. 

 Inlet Pressure Lines: 

All pilots or other devices requiring 

a supply of inlet pressure that can result in a flow of gas 

downstream  of  the  Slam  Shut  must  be  connected  to  the 

center port (port inlet) on the Slam Shut body assembly. A 

shut off valve may be installed in the sense line to prevent 

the Slam Shut valve from closing during setup of regulators 

and other equipment and to aid in setting up the Slam Shut 

valve.

Summary of Contents for Mooney Flowgrid Slam Shut

Page 1: ...Mooney Flowgrid Slam Shut 1 Valve Instruction Manual Rev D Baker Hughes Data Classification Public...

Page 2: ...ICULAR REQUIREMENTS FOR OPERATION OF OTHER EQUIPMENT AT THE SITE THESE INSTRUCTIONS DO NOT PURPORT TO COVER ALL DETAILS OR VARIATIONS IN EQUIPMENT NOR TO PROVIDE FOR EVERY POSSIBLE CONTINGENCY TO BE M...

Page 3: ...essure protection only 2 under pressure protection only and 3 over and under pressure protection Instructions for the Flowgrid regulator and Pilot are found in separate manuals Product Description The...

Page 4: ...ng Case Carbon Steel WCB Throttle Plate 17 4 PH or A515 Slam Shut Seat SST Slam Shut Seal Nitrile Flowgrid Diaphragm Nitrile or Viton Flowgrid Spring SST Slam Shut Housing Slam Shut Spring Cases Alumi...

Page 5: ...hut has all nitrile soft goods VITON The Slam Shut has nitrile static seals and viton dynamic seals and diaphragms MAX INLET Maximum inlet pressure PSIG BAR MIN DIFF Minimum difference in outlet and d...

Page 6: ...m Shut valve and or Flowgrid regulator should be made by qualified personnel familiar with high pressure piping and pilot operated regulators 2 Prior Inspection Inspect the Slam Shut valve regulator p...

Page 7: ...a handle pull the shaft into the reset position 6 With the shaft held in the reset position push the reset pin The trip mechanism will then snap into place 7 Replace the bleed cap reset cap and clear...

Page 8: ...bottle into the Slam Shut Sense Port and apply a constant pressure above the Underpressure set point and below the Overpressure set point if applicable See Figure 5 3 Follow the Resetting the Slam Sh...

Page 9: ...cy of the inspection and replacement of the parts depends on the severity of the service conditions and or the applicable government requirements Inspect all parts for wear and damage Replace all worn...

Page 10: ...dry Replacement of Seals in Underpressure Assembly 1 Turn adjusting screw 2 Use 1 2 wrench to remove four cap screws from spring case with Low Trip labeled on the actuator block 3 Use 9 16 wrench to...

Page 11: ...ccessories if applicable 2 Use 13 16 wrench to remove the four cap screws on the top plate 3 Remove the parts from the body 4 Inspect and or Replace the following seals Body Seals Qty 2 Re install dry...

Page 12: ...owgrid Sense Line Outlet Figure 9 Pressure reducing Flowgrid with Slam Shut downstream overpressure protection Figure 10 Pressure reducing Flowgrid with Slam Shut downstream underpressure protection S...

Page 13: ...over 60 psid 4 bar Inlet Flowgrid Sense Line Outlet Slam Shut Sense Line Outlet Outlet Inlet Flowgrid Sense Line Slam Shut Sense Line Inlet Outlet Outlet Slam Shut Sense Line Inlet Flowgrid Sense Lin...

Page 14: ...r Seal Plate O ring Damaged sealing surface Damaged Sense Port Adapter O ring Fails External Leakage Test out of Bleed Assembly Damaged Bleed Cap O ring Damaged Bleed Stem O ring Damaged Sealing Surfa...

Page 15: ...Mooney Flowgrid Slam Shut 1 valve Instruction Manual 13 Copyright 2021 Baker Hughes Company All rights reserved Notes...

Page 16: ...formation The Baker Hughes logo Flowgrid Slamshut and Mooney are trademarks of Baker Hughes Company Other company names and product names used in this document are the registered trademarks or tradema...

Reviews: