INSTALLATION
IMPORTANT:
Consider the following when looking for a suitable location to place the machine:
•
Overall weight of the machine.
•
Weight of material being processed.
•
Sizes of material to be processed through the machine.
•
Space needed for auxiliary stands, work tables, or other machinery.
•
Clearance from walls and other obstacles.
•
Maintain an adequate working area around the machine for safety.
•
Have the work area well illuminated with proper lighting.
•
Keep the floor free of oil and make sure it is not slippery.
•
Remove scrap and waste materials regularly, and make sure the work area is free from
obstructing objects.
•
If long lengths of material are to be fed into the machine, make sure that they will not extend
into any aisles.
•
LEVELING:
The machine should be sited on a level, concrete floor. Provisions for securing it
should be in position prior to placing the machine. The accuracy of any machine depends on
the precise placement of it to the mounting surface.
•
FLOOR:
This machine distributes a large amount of weight over a small area. Make certain
that the floor is capable of supporting the weight of the machine, work stock, and the
operator. The floor should also be a level surface. If the unit wobbles or rocks once in place,
be sure to eliminate by using shims.
•
WORKING CLEARANCES:
Take into consideration the size of the material to be
processed. Make sure that you allow enough space for you to operate the machine freely.
•
POWER SUPPLY PLACEMENT:
The power supply should be located close enough to the
machine so that the power cord is not in an area where it would cause a tripping hazard. Be
sure to observe all electrical codes if installing new circuits and/or outlets.
Levelling Feet
1. Remove the machine from the pallet and install the leveling feet.
2. Once the machine is moved to its location, level the machine keeping firm even contact on
all four feet.
Summary of Contents for PH-28HD
Page 20: ...18 18 PLATE ASSEMBLY...
Page 21: ...19 19 SLEEVE SPACER POST 1 2018...
Page 22: ...20 20 UPPER LOWER RAM ASSEMBLY...
Page 23: ...21 21 SPROCKET ASSEMBLY...
Page 24: ...22 22 SPRING ASSEMBLY...
Page 25: ...23 23 LEVER ASSEMBLY...
Page 26: ...24 24 SLIDE STROKE ASSEMBLY...
Page 27: ...25 25 QUICK RELEASE ASSEMBLY...
Page 28: ...26 26 TIMING BELT ASSEMBLY PRE JAN 2018...
Page 29: ...27 27 ELECTRICAL BOX ASSEMBLY PRE JAN 2018...
Page 30: ...28 28 GUARD ASSEMBLY PRE JAN 2018...
Page 31: ...29 29 V BELT ASSEMBLY POST JAN 2018...
Page 32: ...30 30 GUARD AND CONTROL BOX ASSEMBLY POST JAN 2018...
Page 39: ...37 37 NOTES...