background image

pBS2120 Base Station Installation Guide 

The pBS2120 interface indicators are described in Table 1-2. 

Table 1-2 pBS2120

 Interface Indicators

 

Identity 

Color 

Status 

Description 

PWR 

Green 

Steady On 

Power On 

OFF 

No Power Supply 

ACT 

Green 

Steady On 

The cell is activated. 

OFF 

The cell is not activeated. 

RUN 

Green 

Fast flash: 0.125s 

on,0.125s off 

The board is loading. 

Slow flash: 1s on,1s 

off 

The board is normal. 

OFF 

No power input or board fault 

ALM 

Red 

Steady On 

Hardware alarm, e.g. VSWR alarm 

OFF 

No alarm 

 

Technical Specification 

1.4

1.4.1  Hardware Specification 

Item 

Description 

LTE Mode 

LTE TDD 

LTE Frequency 

3650 MHz ~ 3700 MHz 

Channel Bandwidth 

10 MHz, 20 MHz 

Output Power 

2

3

 dBm

±

1

dB 

Receiving sensitivity  -101 dBm 

Synchronization 

Mode 

GPS synchronization 

Backhaul Mode 

RJ-45 Ethernet backhaul 

MIMO 

2*2MIMO 

Dimension 

248mm (L) * 248mm (W) * 80mm (H) 

Installation Method 

Pole mounted, wall mounted 

Antenna 

Internal high gain antenna(9 dBi) 

Overall Power 

< 20 W 

Weight 

About 2.0kg 

Note: 

The test method of receiving sensitivity is proposed by the 3GPP TS 36.104, which is based on 5MHz 

bandwidth,

 

FRC A1-3 in Annex A.1 (QPSK

R=1/3

25RB) standard. 

Summary of Contents for pBS2120

Page 1: ...01 All rights reserved Baicells Technologies Co Ltd pBS2120 Base Station Installation Guide...

Page 2: ...No part of this specification may be reproduced in any form or means without the prior written consent of Baicells Disclaimer This specification is preliminary and is subject to change at any time wi...

Page 3: ...t of Box Audit 5 3 Installation Preparation 6 Support Materials 6 3 1 Installation Tools 6 3 2 Installation Environment 7 3 3 3 3 1 Locational Requirements 7 3 3 2 Environmental Requirements 7 Personn...

Page 4: ...and operators enterprises and so on Features 1 2 Adopt the integration design of baseband and RF flexible to deploy Based on 3GPP international standard TD LTE technology provide high speed data servi...

Page 5: ...2120 Appearance The pBS2120 interfaces and indicators are shown in Figure 1 2 Figure 1 2 pBS2120 Interfaces and Indicators The pBS2120 interfaces are described in Table 1 1 Table 1 1 pBS2120 Interface...

Page 6: ...dware alarm e g VSWR alarm OFF No alarm Technical Specification 1 4 1 4 1 Hardware Specification Item Description LTE Mode LTE TDD LTE Frequency 3650 MHz 3700 MHz Channel Bandwidth 10 MHz 20 MHz Outpu...

Page 7: ...ing Support Network Management Interface Support TR069 interface protocol Northbound Interface Support Web service Socket FTP and other interface modes MTBF 50000 hours MTTR 1 hour Maintenance Support...

Page 8: ...is consistent with the requirement 2 Base station mounting bracket 1 Fixed with base station 3 Integrated bracket for on pole or on wall 1 Used for fix on pole or on wall 4 U shape clamp 1 Used for fi...

Page 9: ...for Installing Base Station Item Description Ethernet cable Outdoor CAT6 Shorter than 100m 330 feet Ground cable 16mm yellow green wire Installation Tools 3 2 The following tools are needed during the...

Page 10: ...ion can be chosen to meet the communication engineering environmental requirements as well as the technical requirements of network planning and communication equipment 3 3 2 Environmental Requirement...

Page 11: ...operate the equipment This equipment has been tested and found to comply with the limits for a Class A digital device pursuant to part 15 of the FCC Rules These limits are designed to provide reasona...

Page 12: ...aux deux conditions suivantes 1 l appareil ne doit pas produire de brouillage et 2 l utilisateur de l appareil doit accepter tout brouillage radio lectrique subi m me si le brouillage est susceptible...

Page 13: ...r of the pole 40mm 100mm 1 As the following figure assemble the bracket for pole installation and fasten screws 2 Mounting bracket installs is complete as shown in the following figure 3 Fit the base...

Page 14: ...12mm diameter and 80mm depth holes in the wall by following the marked locations 3 Check the up down direction of the installation rack and then fix the base station to the wall using M8 80 expansion...

Page 15: ...ects to the PoE power adaptor 4 3 2 Connect Ground Cable Make the grounding cable according the actual situation of the installation site The grounding screws of pBS2120 located on the bottom of the b...

Page 16: ...Table 5 1 Table 5 1 pBS2120 Indicator Description Identity Color Status Description PWR Green Steady On Power On OFF No Power Supply ACT Green Steady On The cell is activated OFF The cell is not acti...

Reviews: