background image

Finished grade

12”

Finished grade

8 3/4”

LINE

12V

FIXTURE

COM

Remote

Transformer

COM

Screws on faceplate will 

align with alignment 

arrows on temporary 

cover

Stability flange

Rebar or stake (by others)

Pea gravel or sand

Finished grade

Concrete

Stability flange

Rebar or stake (by others)

Pea gravel or sand

Finished grade

Concrete

Finished grade

Concrete

Wire nuts must 

clear opening

6” 

min.

Finished grade

15”

5.  Align holes to final installation orientation. 

Arrows on temporary cover point towards 

screw location on faceplate for alignment 

purposes.

 

NOTE: Do not remove temporary cover until 

installation of faceplate.

Finished grade

12”

Finished grade

8 3/4”

LINE

12V

FIXTURE

COM

Remote

Transformer

COM

Screws on faceplate will 

align with alignment 

arrows on temporary 

cover

Stability flange

Rebar or stake (by others)

Pea gravel or sand

Finished grade

Concrete

Stability flange

Rebar or stake (by others)

Pea gravel or sand

Finished grade

Concrete

Finished grade

Concrete

Wire nuts must 

clear opening

6” 

min.

Finished grade

15”

1.  Excavate trench according to designed 

lighting plan 12” deep and 12” wide suitable 

for the fixture housing. 

2.  Supply low voltage wiring necessary for 

installation.

3.  Slide stability flange onto housing.

 

NOTE: Product is supplied with a 

stability  flange to anchor fixture and aid in 

installation.

4.  Loop minimum of 6” of low voltage wire inside 

housing to allow for fixture service. Place 

fixture in hole.

 NOTE: 

 

Do not remove temporary cover! 

Fixture Installation

6.  Per DIG-IT Guide, backfill the gap between 

the bottom of housing and bottom of hole with 

sand or pea gravel for drainage.

 

NOTE: The mounting collar must be flush to 

finished grade. Use stability flange to aid in 

installation as shown.

Stability flange

Rebar or stake (by others)

Pea gravel or sand

Finished grade

Concrete

Stability flange

Rebar or stake (by others)

Pea gravel or sand

Finished grade

Concrete

7.  Fill the hole around the fixture housing to 12” 

below the finished grade with clean fill dirt and 

tamp carefully to prevent settling of fixture. 

Pour concrete and finish as required flush with 

mounting collar.

RELEASE DATE

12/15/2021

REFERENCE NUMBER

INS-2317-00

40429 Brickyard Drive • Madera, CA 93636 • USA

559.438.5800 • FAX 559.438.5900 

www.bklighting.com • [email protected]

IMPORTANT SAFETY INFORMATION LISTED ON REVERSE

READ, FOLLOW, AND SAVE ALL SAFETY AND INSTALLATION INSTRUCTIONS

B-K LIGHTING

 

ARTISTAR UPLIGHT

Flush Mount

Standard Installation

Soil Prep

Conduit

trench

B.  Dig hole 10” wide and 10” deep.

Conduit

Trench

Excavated 

for Housing

C.  Prep soil according to DIG-IT Guide.

A.  Determine Soil Type by referencing DIG-IT 

Guide. Prep soil according to DIG-IT Guide.

Reviews: