5. Align holes to final installation orientation.
Arrows on temporary cover point towards
screw location on faceplate for alignment
purposes.
NOTE: Do not remove temporary cover until
installation of faceplate.
Finished grade
12”
Finished grade
8 3/4”
LINE
12V
FIXTURE
COM
Remote
Transformer
COM
Screws on faceplate will
align with alignment
arrows on temporary
cover
Stability flange
Rebar or stake (by others)
Pea gravel or sand
Finished grade
Concrete
Stability flange
Rebar or stake (by others)
Pea gravel or sand
Finished grade
Concrete
Finished grade
Concrete
Wire nuts must
clear opening
6”
min.
Finished grade
15”
1. Excavate trench according to designed
lighting plan 12” deep and 12” wide suitable
for the fixture housing.
2. Supply low voltage wiring necessary for
installation.
3. Slide stability flange onto housing.
NOTE: Product is supplied with a
stability flange to anchor fixture and aid in
installation.
4. Loop minimum of 6” of low voltage wire inside
housing to allow for fixture service. Place
fixture in hole.
NOTE:
Do not remove temporary cover!
Fixture Installation
6. Per DIG-IT Guide, backfill the gap between
the bottom of housing and bottom of hole with
sand or pea gravel for drainage.
NOTE: The mounting collar must be flush to
finished grade. Use stability flange to aid in
installation as shown.
Stability flange
Rebar or stake (by others)
Pea gravel or sand
Finished grade
Concrete
Stability flange
Rebar or stake (by others)
Pea gravel or sand
Finished grade
Concrete
7. Fill the hole around the fixture housing to 12”
below the finished grade with clean fill dirt and
tamp carefully to prevent settling of fixture.
Pour concrete and finish as required flush with
mounting collar.
RELEASE DATE
12/15/2021
REFERENCE NUMBER
INS-2317-00
40429 Brickyard Drive • Madera, CA 93636 • USA
559.438.5800 • FAX 559.438.5900
www.bklighting.com • [email protected]
IMPORTANT SAFETY INFORMATION LISTED ON REVERSE
READ, FOLLOW, AND SAVE ALL SAFETY AND INSTALLATION INSTRUCTIONS
B-K LIGHTING
ARTISTAR UPLIGHT
Flush Mount
Standard Installation
Soil Prep
Conduit
trench
B. Dig hole 10” wide and 10” deep.
Conduit
Trench
Excavated
for Housing
C. Prep soil according to DIG-IT Guide.
A. Determine Soil Type by referencing DIG-IT
Guide. Prep soil according to DIG-IT Guide.