20
OM-ECOARCH
Final Air Balance
1. Close all doors and windows.
2. Operate all exhaust fans even those serving other hoods, supply fans, make-up air unit
and building HVAC system.
3. Turn on all cooking equipment under the hood and preheat to operating temperature.
4. Produce large quantities of smoke or steam.
5. Observe capture of vapors.
6. If all vapors are not totally captured, fine tune the system by adjusting the air volume
control damper installed in the supply collar. Slightly reduce the amount of supply air
directed under the hood until full capture is obtained.
MAKE-UP AIR HOODS
Summary of Contents for ecoarch
Page 7: ...OM ECOARCH 7 Installation Instructions Figure 5...
Page 8: ...8 OM ECOARCH Installation Instructions Figure 5 Continued...
Page 10: ...10 OM ECOARCH Installation Instructions Figure 6a RELAY BOX BALLAST BOX...
Page 11: ...OM ECOARCH 11 Installation Instructions Figure 6b...
Page 12: ...12 OM ECOARCH Installation Instructions Figure 6c...
Page 15: ...OM ECOARCH 15 Installation Instructions Figure 7 FOR CONTROL PANEL IF PROVIDED...