Upgrading a Multicarrier G2 Universal Module to Avaya
DEFINITY Server R EPN running Avaya Communication
Manager
555-233-115
5-10
Issue 7 November 2003
Task Tables
,
, and
provide the high-level tasks to perform the
upgrades detailed in this chapter. Refer to the appropriate page for detailed
instructions for each step.
Standard Reliability
Table 5-3.
Tasks to Upgrade Standard Reliability
3
Task Description
Page
Follow Routine Preventive Maintenance
Remove Module Control Carrier(s)
Install Power-Failure Transfer Ground Wire
Remove Circuit Packs from Module Control Carrier A
Remove CURL from Module Control Carrier A
Remove Module Control Carrier A
Install Expansion Control Carrier(s)
Install New Expansion Control Carrier A
Verify Usable Circuit Pack Vintages
Remove Power-Failure Ground Wire
Administer No-License/Emergency Numbers
Continued on next page