Atlantic Boilers ME STANDARD 120 Operating & Maintenance Manual Download Page 18

18

ME Standard Manual

17

7).

   

IDENTIFICATION O

F

SPARE PARTS

        

Controlle

r                                                        

790220

        

Flow senso

r                                                     

583027

        

30kW immersion heate

r                                   

2534

        

35kW immersion heate

r                                   

2536

        

Limit thermostat

                                            

581104

        

Wate

r

flow switch

                                         

480230

8).

   

FAULT DETECTION

        

Before making any physical check, switch off the power

         

FAULT

                                                              

CHECK

        

The ‘live’ light is out

                                    

Chec

k

fo

r

incoming power

                                                                                   

Check fuses F1 and F2

                                                                                   

Check the ‘alive’ bulb

………………………………………………………………………………………………………………………..

         

The controlle

r

screen is out

                        

Check fuse F3

………………………………………………………………………………………………………………………….

         

Step 1 o

r

Step 2 light is out

                         

Change the bulb

………………………………………………………………………………………………………………………….

         

The ‘red’ light is lit

                                         

Chec

k

the limit thermostat

                                                                                    

Chec

k

the wate

r

flow switch action

                                                                                    

Chec

k

the circulating pump overload

…………………………………………………………………………………………………………………………..

         

If the fault remains

                                        

Call in a qualified service engineer

   

  

      

This GUARANTEE is to the PURCHASER of the Boiler(s) who is deemed to be the INSTALLER of the 

Boiler(s).  If the Boiler(s) is(are) purchased by the EVENTUAL USER who then arranges to install the 

Boiler(s), the EVENTUAL USER is deemed to be the INSTALLER.  The details of the GUARANTEE are 

given to assist the INSTALLER in obtaining effective action within the GUARANTEE and they are 

in addition to the INSTALLER’S Legal Rights under the relevant statutory enactments for the time 

being in force in England, Scotland, Wales and Northern Ireland.

GAS, OIL, B100 bio-diesel or ELECTRICAL EQUIPMENT

The Replacement or Repair of the item, including the Cost of its Delivery to the site of the 

installation or its equal, provided that the Defect or Flaw occurs within one Calendar Year of the 

Commissioning Date.

REMOVABLE COMPONENTS OF THE BOILER ASSEMBLY   

(other than the gas, oil or electrical equipment)

The Replacement or Repair of the item, including the Cost of its Delivery to the site of 

the installation, provided that the Defect or Flaw occurs within one Calendar Year of the 

Commissioning Date.

 

THE MAIN BODY OF THE BOILER

The repair of any Defect or Flaw in the Main Body of the Boiler including any necessary removal or 

replacement of that part of the Boiler on site if the Defect or Flaw occurs within five calendar years 

of the Commissioning Date

DEFINITIONS

The effective actions stipulated in this guarantee are subject are subject to the PURCHASER 

complying completely with the following :-

1.  The Boiler(s) is(are) installed according to the Recommendations of the Atlantic Boilers’ Manual,  

 

the Recommended Codes of Practice of the CIBSE, the BSI, the BSRIA. and the Atlantic Boilers’  

 

Commissioning Check List.

2.  The Commissioning of the Boiler(s) by an Atlantic Engineer employed or authorised by

 

Atlantic Boilers, and regular servicing & maintenance according to the Atlantic Boilers’ Manual  

 

& Service Booklet.

3.  The Payment in Full by the Purchaser, unless otherwise agreed, of the invoices for the Supply   

 

of the Boiler(s) as agreed, and the invoices for commissioning and any correction of installation  

 

error, all to be made within agreement terms.

4.  The Presentation at the time of a Claim under the Guarantee, of the Boiler Registration  

 

 

number, the Commissioning Record and the  necessary information for defining any  

 

 

Replacement Part. 

5.  When a Replacement Part is supplied for a Defective Item, the Defective Item must be returned  

 

to Atlantic Boilers at their Head Office within 6 weeks of the Date of Notification of the Defect  

 

and must be carefully labelled with Registration Number of the Boiler together with the Name  

 

and Order Reference of the Purchased of the Boiler. If this is not complied with, the Purchaser  

 

will be charged with the Cost of the Item and its Delivery.

11/05/2015.MW

ATLANTIC 2000 - boilerplant sales  ACM ATLANTIC - commissioning and maintenance  ATLANTIC 4422 – spares

Registered in England.  Company No: 1477687  Vat Reg No: 306 0653 89 Tel: 0161 621 5960 Fax: 0161 621 5966

GUARANTEE

Summary of Contents for ME STANDARD 120

Page 1: ...NDARD ELECTRIC BOILER OPERATING MAINTENANCE MANUAL MODELS 90 120 150 180 210 245 280 315 350 385 420 455 490 525 560 595 630 09 2011 CODE 560955 CE Directive 2006 95 CEE British Standard EN 60335 1 C...

Page 2: ...er room arrangements 10 2 6 Commissioning 10 3 0 ELECTRICAL ARRANGEMENTS 3 1 Control panel arrangement 11 3 2 Control circuitry 12 3 3 Electrical power circuitry 13 3 4 Fuse and overload protection 13...

Page 3: ...working temperature 100 C limit 110 C 50mm thick glass silk insulation with MO fire classification cladding Hand reset limit thermostat at 110 C Resistance to earthing shock not less than 1 megohm IN...

Page 4: ...1360 1360 1360 Width mm 600 600 600 600 800 800 800 800 1000 1000 1000 1000 1000 1000 1000 1000 1000 Height mm 1380 1380 1380 1380 1570 1570 1570 1570 1700 1700 1700 1900 1900 1900 1900 1900 1900 Acc...

Page 5: ...kPA 16 16 16 16 16 16 16 Flow return connections 100 100 100 100 100 100 100 Dry weight kgs 233 238 243 248 253 258 263 Water contents litres 283 283 283 283 283 283 283 DIMENSIONS Depth mm 970 970 9...

Page 6: ...6 ME Standard Manual 1 6 Orientation...

Page 7: ...ng and operation of the immersion heater step controls Switch off the immersion heaters using the main control panel isolator Check that all the cartridge fuses are sound Double check that all the imm...

Page 8: ...Pressure Relief Valve Drain Valve Filling Loop Ball Valve Heating Ball Valve Strainer Pump Non return valve Drain Valve Expansion Vessel Pressure Relief Valve Filling Loop Auto top up system Water fl...

Page 9: ...fer a water flow switch fitted in the same pipeline as the boiler and set to just below maximum flow If the switch registers maximum flow the boiler stops E We recommend an automatic pressurisation un...

Page 10: ...rials leading to electrolytic action and system deterioration The Multi elec Compacte is not suitable for external installation 2 6 Commissioning The boiler must be completely full of water before the...

Page 11: ...CONTROL RELAY TERMINALS T1 T2 T3 STAGE DELAY TIMERS F1 TRANSFORMER SUPPLY FUSES F2 230V FUSES 415V MAINS ISOLATOR F6 STAGE 3 FUSES F5 STAGE 2 FUSES KM2 STAGE 2 CONTACTOR KM3 STAGE 3 CONTACTOR VOLTAGE...

Page 12: ...12 ME Standard Manual 3 2 Control circuitry EXTERNAL CONTROLS 3 2 Control Circuitry...

Page 13: ...0 140 140 175 175 175 175 175 219 OUTPUT STEP THREE 30 30 30 60 70 70 70 105 105 105 140 140 140 175 175 210 210 Fuse ratings and type industrial cylindrical cartridge MODEL 90 280kW FUSES F1 1A type...

Page 14: ...length of run and prevention of short circuit The installation must be tested for automatic power failure in the event of emergency power cut heater lock out or error in the neutral layout All electr...

Page 15: ...circuit breakers and fuses 5 Earth wiring is essential 6 One week after commissioning all connectors on immersion heaters and incoming electrical supplies need to be checked This should be repeated an...

Page 16: ...tor or de scaling agent Minimum maintenance periods A Monthly maintenance i Check operation of the automatic air vent ii Check operation of the water flow switch iii Check operation of the safety valv...

Page 17: ...ny physical check switch off the power FAULT CHECK The live light is out Check for incoming power Check fuses F1 and F2 Check the live bulb The controller screen is out Check fuse F3 Step 1 or Step 2...

Page 18: ...pair of any Defect or Flaw in the Main Body of the Boiler including any necessary removal or replacement of that part of the Boiler on site if the Defect or Flaw occurs within five calendar years of t...

Page 19: ...W are in compliance with European directives Directive 2009 125 CE Eco Design Directive 2010 30 UE Energy Labelling Directive 2014 35 UE Low Voltage Directive 2014 30 UE Electromagnetic compatibility...

Page 20: ...ASHTON UNDER LYNE OL6 7TR T 0161 621 5960 E technicalsales atlanticboilers com FOR TECHNICAL HELP ADVICE Call 0161 621 5960 or email technical atlanticboilers com FOR FULL PRODUCT RANGE LITERATURE Vis...

Reviews: