52
107750-01 - 9/17
Figure 7.34: PolyPro Locking Band Installation
VII. Venting
F. Assembly of DuraVent PolyPro Vent Systems (continued)
F. Assembly of DuraVent PolyPro Vent Systems
1. This boiler has been listed for use with the DuraVent PolyPro single wall PolyPropylene vent system to be provided by the
installer.
WARNING
Asphyxiation Hazard. Follow these instructions and the installation instructions included by the
original PolyPropylene venting component manufacturers, M&G/DuraVent. Failure to do so could
cause products of combustion to enter the building, resulting in severe property damage, personal
injury or death. Where a conflict arises between M&G/DuraVent instructions and these instructions,
the more restrictive instructions shall govern.
Do not mix vent components or joining methods for listed manufacturers.
Examine all components for possible shipping damage prior to installation.
All condensate that forms in the vent must be able to drain back to the boiler.
2. Assemble the vent system, starting at the boiler:
a. The vent adaptor has three different inside diameters. The middle inside diameter accepts 4" nominal PolyPro (Figure
7.26). Lubricate the gaskets in the vent adaptor with soapy water and insert the first piece of 4" PolyPro into the adaptor
until it bottoms out. Tighten band clamp on vent adapter to secure vent pipe.
b. If 3" PolyPro is to be used for the vent system, reduce the first piece of 4" PolyPro installed in Step (a) to 3" using
DuraVent #4PPS-R3. Otherwise assemble the next piece of 4" PolyPro.
c. For each joint, verify that the gasket is evenly seated in the bell (female) end of the pipe. Lubricate this gasket with water.
Slide a locking band over the male end of the pipe to be joined as shown in Figure 7.34. Push the male end of the next
section of pipe into the bell until it bottoms out, then back out 1/4-5/8" to provide room for thermal expansion. Push barb
on locking band over the bell end of the first section of pipe as shown in Figure 7.34.
d. Assemble the rest of the vent system per the manufacturer’s installation instructions, being sure to pitch horizontal
sections back towards the boiler 5/8" per ft (53 mm/m).
e. Support each horizontal pipe section with a minimum of one wall strap each and at intervals not exceeding 4ft.
Summary of Contents for ASPN-320
Page 88: ...88 107750 01 9 17 Figure 10 4 Proper Installation of Header Sensor X Wiring continued ...
Page 89: ...89 107750 01 9 17 Figure 10 5 Internal Wiring Ladder Diagram X Wiring continued ...
Page 90: ...90 107750 01 9 17 X Wiring continued CONDENSATE FLOAT SWITCH ...
Page 91: ...91 107750 01 9 17 X Wiring continued Figure 10 6 Internal Wiring Connections Diagram ...
Page 100: ...100 107750 01 9 17 Operating Instructions XI Start Up and Checkout continued ...
Page 145: ...145 107750 01 9 17 XV Service Parts continued ...
Page 147: ...147 107750 01 9 17 XV Service Parts continued All Models ...
Page 149: ...149 107750 01 9 17 XV Service Parts continued All Models ...
Page 151: ...151 107750 01 9 17 XV Service Parts continued All models ...
Page 157: ...157 107750 01 9 17 ...
Page 158: ...158 107750 01 9 17 ...
Page 159: ...159 107750 01 9 17 ...