Installation Instructions – ASPEN 1900 Series Mid-Sized Bollard
ADL141353 www.eaton.com
Figure 3.
Step 2: Anchor Bolt Installation
1. Disconnect or turn fixture power OFF prior to
performing all installation and maintenance activities.
Trench as appropriate and place conduit as required
by the National Electric Code and any other applicable
rules, regulations, and requirements. Ensure that
there is enough depth in trench to accept anchor bolt
assembly.
2. Remove the external sleeve from the fixture base.
Locate anchor bolt assembly.
3. Place anchor bolt assembly (three anchor bolts
attached to pad plate with nuts) over conduit and
secure for concrete pour. Make sure that the pad
plate is flush with the concrete surface, and that the
assembly will not be dislodged during concrete pour
operations. (Figure 3.) The base has been designed
to accept two (2) conduits for daisy chaining when
necessary.
ote:
N
Ensure that there is enough thread length above
the pad plate to accept the fixture base and
neoprene pad, and to allow 2” to protrude from the
top of the base. (Figure 4.)
4. Pour concrete. Make sure that pad plate is as level as
possible. Allow concrete to cure.
2”
Conduit
Figure 4.
Pad Plate on surface
of concrete
Figure 5.
1. To level the base, adjust the top three lock nuts.
2. As you tighten the nuts, the base compresses the
underlying neoprene pad for quick and easy leveling.
Step 4: Leveling Base
1. Pull line-voltage wire leads through the conduit and
fixture base and make connection to component
frame assembly input leads (LED module shown)
(Figure 6.) Connect supply wires to appropriate
luminaire leads.
•
Supply side ground wire to green luminaire lead.
•
Supply side neutral wire to white luminaire lead.
•
Supply side line voltage
wire to black luminaire lead.
2. Secure the external sleeve
to the base by tighten
the three (3) counter-
sink screws. (Figure 7.)
Recommend tightening
by hand as to not strip the
screw
Step 5: Connecting to Power
1. Remove the top three nuts from the anchor bolts.
(Figure 5.)
2. Place the base mounting pad and base onto the bolts.
3. Replace the top three nuts with the supplied lock nuts
to ensure that the base remains secure to the anchor
bolts.
Step 3: Base Installation
Base
Base Mounting Pad
Figure 6.