Pool Chemicals Connection
At this step is necessary to connect the injecting valves of individual
chemicals to the dosing pumps and dosed agents.
Place the injecting valve in the T-joint, blinded with the
DN50 G1/4” threaded
plug #12134.
1.
Cut the PE tube at 90 ° angle to ensure proper fitting.
•
Use the sharp knife to cut plastic. The cut must be clean and smooth.
2.
Drill the 6 mm hole and the 1 mm hole (air suction) into the CHLORPURE
canister cap. Push the PE tube through the cap. Select the tube distance
so that the tube reaches the canister bottom and can be connected to
the pump as straight as possible. A long tube in the canister would bend
and produce air bubbles.
3.
Put a weight on the tube end and dive it in the canister.
4.
Connect the plastic tube from the CHLORPURE canister to the
ASIN AQUA Home pump (marked as 1 CHLORINE) to the left connection.
5.
Connect the plastic tube to the 1 CHLORINE pump right connection and
the injection valve.
6.
Hand screw the CHLORPURE injection valve in the specified mounting
hole (see diagram).
•
The injection valve is installed in G 1/4” thread.
To connect dosing of pH, algaecide and flocculant, repeat steps 1 to 6 for
other pumps according to their marking.
•
Check throughput of the injection valves and tightness of the entire
system (see installation test).
WARNING:
Only hand tighten. Do not use tongs or any other tools.
T-joint with inserting
DN50 plug G1/4”
threaded
Injecting valve
Drills
Wrong installation