Oven stand continued
The top to the stand now needs to be poured,. Use a 4ft x 4ft x 1/2” sheet of cement board as the floor of
the frame. A frame work of 2” x 6” boards will be needed as an outer frame and also 2” x 4” supports on
the inside to prevent the cement board deflecting under the weight of concrete. This is supported by vertical
studs from the foundation.
Cut 1/2” rebar to fit inside the top of the stand before pouring the stand top (set on 12” centres)
The cement board remains as part of the stand. After a couple of days remove the form work and the
internal supports. Finish the sides of the stand as desired with render, cultured stone etc . It is
recommended to finish the top with waterproof tile,. This can be ceramic tile or natural stone or granite tile.
It is important that the top be level and completely flat.