Argo AT062310B Installation Procedure Download Page 2

6

System should be designed as primary/secondary piping 

and to operate with a maximum output temperature of 

180ºF or lower and a temperature rise across the unit 

of 20ºF or lower. Refer to tables below and Figures 2 
& 3.

“AT” Series - 2 Element Boiler

KW Capacity

Minimum Flow Rate (GPM)*

6

2.0

8

2.7

10

3.4

12

4.1

“AT” Series - 4 Element Boiler

KW Capacity

Minimum Flow Rate (GPM)*

12

4.1

16

5.5

20

6.8

24

8.2

* Flow rate based on 20°ΔT

CONNECTINg SUPPLy AND RETURN PIPINg

1.  Maintain  minimum  clearance  of  one  inch  to  hot 

water pipes.

2. Hot water boilers installed above radiation level must 

be provided with low water cutoff device either as 

part of boiler or at time of boiler installation.

4. Suggested plumbing arrangements are illustrated in 

Figures 2 & 3. Inlet or return pipe is located at bottom 

of unit. Reverse flow will result in noisy operation 

and cause very early element failure.  Drain cock is 

to be located at lowest point of piping.

5. Outlet or supply pipe line to radiation is located at top 

of unit. Combination temperature pressure (altitude) 

gauge  is  provided  with  each  unit  and  should  be 

installed close to boiler outlet. It is important gauge 

sensor  be  completely  immersed  in  flowing  water 

to assure correct temperature readings. Manual or 

automatic water make up supply may be located in 

this area below. Circulator pump should be installed 

on supply side (pumping away).

6. Install gate valves at locations shown in Figures 2 

&  3,  so    any  boiler  servicing  requiring  removal  of 

water can be done quickly and easily. Not illustrated 

but recommended is installation of air vents at high 

points of hydronic system. Devices will reduce initial 

start up time and help avoid element burnout during 

entire life of heating system.

7. Pressure relief valve is supplied with each Electric 

Hydronic Block and should be installed at the location 

and discharge direction shown  in 

Figure 1

, using 

pipe  nipple  and  elbow  supplied.  Piping  should  be 

added so that any water discharged will not damage 
boiler or other system components.

PLUMBINg AND

ACCESSORy

INSTALLATION

8. For further piping information refer to Hydronics        

    Institute (I=B=R) manual 200 (Installation guide  

    for Residential Hydronics).

figurE 1

3. When boiler is connected to heating system utilizing 

multiple  zone  circulators,  each  circulator  must  be 

supplied with flow control valve to prevent gravity 

circulation.

dEsign of WATEr circuLATing sysTEm

NOTICE

Return water temperature must be higher 

than room temperature in which boiler is 

installed to prevent condensation.

NOTICE

In some states low water cutoff device 

(LWCO) may be required. Check your local 

codes.

NOTICE

Reduced pressure back flow preventer must 

be present under provisions required by 

Environmental Protection Agency, (EPA).

Summary of Contents for AT062310B

Page 1: ...ting brackets for easy wall mounting Use of lag screws or anchor bolts through holes provided or on 3 4 plywood panel On uneven walls suggested mounting surface be provided such as two 2 x 4 s Surface...

Page 2: ...p supply may be located in this area below Circulator pump should be installed on supply side pumping away 6 Install gate valves at locations shown in Figures 2 3 so any boiler servicing requiring rem...

Page 3: ...7 primary secondary piping for Multiple zoning with ZONE VALVES primary secondary piping for Multiple zoning with circulators PRIMary secondary piping figure 2 figure 3...

Page 4: ...e ends before inserting into terminal block Tighten terminal screws Do not use pump rated greater than 5 amps Thermostat Connect thermostat or zone valve end switch to terminals TT and TT Figure 4 Do...

Page 5: ...re sizes specified conform to Canadian Electrical Code Canada or National Electric Code USA and include derating for ampacity and temperature Use copper wire only Check state and local requirements Re...

Page 6: ...or will continue to be energized for 3 minutes to purge boiler After 3 minutes control will de energize circulator Circ LED turns off If during start up or during operation safety end switch opens its...

Page 7: ...TACT SEC 120 VOLT WIRING POSE DES C BLES 120 VOLT 240 VOLT WIRING POSE DES C BLES 240 VOLT 120 VOLT FIELD WIRING POSE DES C BLES 120 VOLT SUR EN CHANTIER 240 VOLT FIELD WIRING POSE DES C BLES 240 VOLT...

Page 8: ...HERS SOURCE DU COURANT 120V 60HZ 1PH OU AUTRES OPTIONAL FLOW SWITCH BY OTHERS INTERRUPTEUR DE D BIT FACULTATIF OU AUTRES THERMOSTAT BY OTHERS THERMOSTAT OU AUTRES ELEMENT 1 L MENT No1 ELEMENT 1 RELAYS...

Page 9: ...T BLK BLANC NOIR WHT BLANC FUSE BLOCK BLOC DE FUSIBLE BLK NOIR L2 L1 POWER BLOCK BLOC DE PUISSANCE 240 VOLT FIELD WIRING POSE DES C BLES 240 VOLT EN CHANTIER EN CHANTIER 120 VOLT WIRING POSE DES C BLE...

Page 10: ...NOIR WHT BLANC RED ROUGE WIRE LEGEND L GENDE DES FILS DRY CONTACT WIRING POSE DES C BLES DE CONTACT SEC 120 VOLT WIRING POSE DES C BLES 120 VOLT 240 VOLT WIRING POSE DES C BLES 240 VOLT 120 VOLT FIELD...

Page 11: ...as the pressure remains less than 25 PSIG Hydronic block is now ready to be put into service Verify hydronic block circuit breaker or switch at service 1 entrance and depending on option hydronic blo...

Page 12: ...cluded with this manual Turn off hydronic unit circuit breaker at service en 1 trance and or disconnect switch Close gate valves near inlet and outlet of hydronic 2 block noisy boiler heating element...

Reviews: