4. Load Cell Installation
PNEG-2340
Feed-Link 2
17
Running Load Cell Cables
1. Label both ends of the load cell cable with the
load cell number. Numbers will range from
1 through 8. Labeling the load cell cables will
identify what terminals to use when connection
wires to display unit in installing the stand
alone display units on
. It will also
expedite troubleshooting if any problems
should arise.
2. Run cable from the load cell up bin leg using
wire ties (not included) to fasten into place.
Run cable along the cross brace to the center
of the bin. Then take cable around the bin boot
and back up the leg that the display or junction
box is mounted to
and
3. Repeat
for each load cell.
Figure 4K
Fasten Wires with Wire Ties
Figure 4L
Run wire tie through holes in
bin legs to attach cable to legs
.
Figure 4M
Run wires around the boot of the bin
.