Installation Checklist
Installation
3.2 Installation Checklist
Table 3.1 provides an installation checklist for installing, wiring, and testing the IQ-636X-2/E
system. It has references to installation information included in manuals listed in Section 1.3
“Related Documents”.
3.3 Mounting a Cabinet
This section provides instructions for mounting a CAB-4 Series backbox to a wall. Follow these
guidelines when mounting the backbox:
•
Locate the backbox so that the top edge is 66 inches (1.6764 m) above the surface of the
finished floor.
•
Access to the cabinet shall be provided in accordance with NFPA 90, article 110.33.
•
Allow sufficient clearance around cabinet for door to swing freely. (See Section 2.3 “System
Cabinets”.)
•
Use the four holes in the back surface of the backbox to provide secure mounting. (See
Figure 3.1.)
Seq
Task
Refer to
1.
Mount the cabinet backbox to the wall.
Section 3.3 “Mounting a Cabinet”
2.
Install hinges for door
CAB-3/CAB-4 Series Cabinet Installation Document
3.
Install all required chassis in cabinet.
Section 3.5 “Installing the Control Panel”
4.
Install control panel onto chassis.
Section 3.5.1 “Control Panel Circuit Board &
Keypad/Display Unit”
5.
Optional: Install auxiliary power supply and/or external
battery charger
Auxiliary power manuals
6.
Connect AC wiring, place batteries into backbox without
connecting them, and run cable to optional power supplies,
DC power outputs, NACs, and relays.
CAUTION: Do not apply AC or DC power at this time.
Section 3.7 “Connecting the Power Cables”
7.
Set switches for backup alarm (SW1-SW4).
Section 3.10 “Backup-Alarm Switches”
8.
Optional: Install option boards, and annunciators,
Section 3.6, “Mounting Option Boards”, the relevant
annunciator/ manual,
9.
Optional: Install output devices such as a printer, or CRT
terminal.
Section 3.13 “Installing Remote Printers and/or CRT”
10.
Optional: Install AutoPulse-NCA-2.
AutoPulse-NCA-2
Manual,
11.
Secure any unused mounting holes in control panel
circuit board.
Figure 3.6
12.
Wire the Signaling Line Circuits.
Section 3.14 “Wiring a Signaling Line Circuit (SLC)”
13.
Terminate wire shielding as instructed.
SLC Wiring Manual
14.
Apply AC power to the control panel by placing the external circuit breaker to the ON position.
Do NOT connect batteries
.
15.
Check AC power.
Table 3.5 in Section 3.7 “Connecting the Power Cables”
16.
Connect the batteries using interconnect cable, P/N 75560 and 75561.
17.
Install the CAB-4 series door.
CAB-3/CAB-4 Series
Cabinet Installation Document
18.
Program the control panel.
IQ-636X-2/E Programming Manual
19.
Field test the system.
Section 5 “Testing the System”
Table 3.1 Installation Checklist