background image

ASSEMBLY AND INSTALLATION

INSTALLING AZ/EL CAP MOUNT ONTO POLE

The AZ/EL Cap is factory preassembled, therefore, no
assembly is required. Before installing AZ/EL Cap onto
ground pole, a concrete foundation should be in place
and cured.

MODEL 611612001 (Fine Tune Option)

Loosen (8) Carriage Bolts and nuts securing the “U”
Bracket to the Top Bracket and “U” Bracket to (2) half
clamps and swivel nut, hex nut (for optional fine tune fea-
ture). (Ref. Fig. 1.0). Install AZ/EL Cap Mount onto
Ground Pole. Equally tighten (4) Clamp Bolts so that
Cap is held stationary on Ground Pole, but can be
swiveled with slight pressure (approximately 2 ft-lbs (2.7
N-m). Retighten and torque (4) Carriage Bolts and nuts
securing “U” bracket to half clamps to 18 ft-lbs (24.4 N-
m). Leave loose (4) Carriage Bolts and Swivel Nut, Hex
Nuts, for fine tune option.

MODEL 611612002 (w/o Fine Tune Option)

Make sure (4) carriage bolts and nuts securing the
(2) Half Clamps to top bracket are loose.

(Ref. Fig.

1.1) Place AZ/EL Cap onto Ground Pole and tighten (4)
Half Clamp Bolts to approximately 2 ft-lbs (2.7 N-m) (just
enough to allow AZ Clamp to turn on pole with slight
pressure). Tighten and torque (4) Carriage Bolts and
Nuts in Top Bracket to 18 ft-lbs (24.4 N-m) (loosened
above).

ASSEMBLING REFLECTOR ONTO AZ/EL CAP MOUNT

96cm System

Install two M8 x 56 (56 mm) Plow Bolts into holes in
Reflector Face and two (91 mm) into bottom holes.
Lift Reflector and insert exposed portion of bolt into
holes into Antenna Bracket Flange. Install 4 Lock
Washers and Hex Nuts on bolts. (Ref. Fig. 1.2)

1.2m System

Install four M8 x 91 (91 mm) Plow Bolts into top holes
in Reflector Face. Lift Reflector and insert exposed
portion of bolt to holes in Antenna Bracket Flange.
Install 4 Lock Washers and Hex Nuts on bolts. (Ref.
Fig. 1.2)

Assemble Extension Plate to AZ/EL Housing using
two M6 x 22mm Round Head Square Neck Bolts,
Lock Washers, and Hex Nuts. (Ref. Fig. 1.3) Tighten
and torque to 6 ft-lbs (8 N-m).

Tighten and torque Reflector bolts to 11 ft-lbs (15 N-m).

IMPORTANT:

Note orientation of bolt holes in Reflector

Flange. Holes should be located on each side and bot-
tom of the Reflector as shown in Figure 1.2.

TOP BRACKET

"U" BRACKET

HEX NUT,
CARRIAGE BOLT (8)

HALP CLAMP (2)

CLAMP BOLTS
(CARRIAGE BOLT &
HEX NUT) (4)

HEX NUT

SWIVEL NUT

FIG. 1.0 - Model 611612001 AZ/EL w/Fine Tune

Option

(2 REQ)

PLOW BOLT

M8 x 1.25 x 56

(.96m ONLY)

(2 REQ) .96m

PLOW BOLT

M8 x 1.25 x 91
(QTY. 4, 1.2m)

SIDE BOLT

HOLE

BOTTOM

BOLT

HOLE

GROUND

POLE

CLAMP

BOLTS

HEX NUT

(4 REQ)

LOCK WASHER

(4 REQ)

MOUNT ASSEMBLY

FIG. 1.2 - Assembling Reflector to AZ/EL Mount

and Ground Pole (.96cm Shown)

CLAMP BRACKET

HEX NUT,
CARRIAGE BOLT (4)

HALF CLAMP (2)

CLAMP BOLTS
(CARRIAGE BOLT &
HEX NUT (4)

FIG. 1.1 - Model 611612002 AZ/EL w/o Fine

Tune Option

5

APPENDIX A

96cm Antenna Survival Windloads at 125 MPH Velocity

Mo Based on 41.5" (1054 mm) from Mounting Surface of Center Line of Antenna

Values shown represent maximum forces for any wind direction and 
include 1.5 Fs. Height and exposure factors from uniform building code

are NOT included.

F

H

= Horizontal Force

F

V

= Vertical Force

M

T

= Torsional Moment

M

O

= Overturning Moment

BEA

M A

XIS

MECHANICAL AXIS

(NORMAL TO ANTENNA FACE)

15.4

o

OFFSET

41.5" HEIGHT

(1054 mm )

FH

MT

FV

MO

ELEVATION DEGREES

MECHANICAL

  BEAM

0

15

10

25

20

35

30

45

40

55

50

65

60

75

70

85

FORCE (POUNDS)

F

H

F

V

747

-20

707

-150

687

-289

622

-413

548

-498

478

-548

398

-573

299

-443

MOMENTS (FT-LBS/N-m)

M

T

M

O

150

2584

147

2445

139

2376

126

2151

107

1896

90

1653

70

1377

54

1034

12

Summary of Contents for 123 Class I

Page 1: ...SA Customer Support Center From North America Telephone 1 800 255 1479 Fax 1 800 349 5444 satcom andrew com One Company A World of Solutions International Telephone 1 708 873 2307 Fax 1 708 349 5444 I...

Page 2: ...iately upon failure Non compliance with any part of this claim procedure may invalidate this warranty in whole or in part THIS WARRANTY IS EXPRESSLY IN LIEU OF ALL OTHER AGREEMENTS AND WARRANTIES ANY...

Page 3: ...required before installing an antenna It is the property owner s responsibility to obtain any and all permits Before any digging is done information regarding the possi bility of underground telephone...

Page 4: ...foot c Lateral soil pressure of 400 pounds per square foot d Concrete compressive strength of 2500 pounds per square inch in 28 days 2 CAUTION The foundation design shown does not represent an approp...

Page 5: ...protection 1 Pole and foundation design based on the following criteria a Uniform building code exposure B or C and 1 5 stability factor b Vertical soil pressure of 2000 pounds per square foot c Late...

Page 6: ...lector and insert exposed portion of bolt to holes in Antenna Bracket Flange Install 4 Lock Washers and Hex Nuts on bolts Ref Fig 1 2 Assemble Extension Plate to AZ EL Housing using two M6 x 22mm Roun...

Page 7: ...nd Hex Nuts Round Head Square Bolt fits on the underside of Mount Housing top flatten end of Brace on top side of Mount Housing Tooth Lock Washer on top of flatten end of Brace then Flat Washer and He...

Page 8: ...or and Support Block to 4 ft lbs 5 4 N m Tighten and torque M6 x 55mm U Bolt to 18 22 in lbs 2 2 5 N m TOOTH WASHER BLOCK U CLIP BRACE SIDE FEED LEGS 2 REQ RD HD SQ NK BOLT ELASTIC LOCK NUT BOTTOM FEE...

Page 9: ...ion and counterclockwise to increase elevation Align the edge of the Clamp with appropriate mark on housing at the desired elevation reading This will be an approximate setting Optimum setting achieve...

Reviews: