Maintenance 

 

CHANGING THE FILTER 

 

CAUTION: THIS PROCEDURE CAN CAUSE SEVERE BURNS. USE PROPER 
PROTECTION. 

 

Changing the filter in the Model 270 Heated Filter Assembly is extremely easy. Using gloves to protect the 
hand, grasp the cap on the end of the filter body opposite the probe and turn it counterclockwise. The cover 
may be hot to the touch and may cause burns to the hand if not protected. Removing the cover exposes the 
filter. The cover is secured to the assembly with a retainer chain. Reach into the heated oven with pliers to 
pull out the old filter.  

Inspect the O-Rings which are at each end of the filter to ensure they are still elastic and will seal the filter. 
Replace O-Rings if they are charred or deformed. 

Replace the filter with a new one, again handling it with pliers. Ensure that the filter is pushed in the center of 
the oven so that it is in contact with the O-Ring on the far end of the filter. Screw the cap back on the filter 
body. The filter replacement procedure is complete.

  

 

NH

3

 CONVERTER 

The NH

3

 Converter requires relatively little maintenance, but over a long period of time (years), the 

effectiveness can drop off due to oil and oxidation coatings on the internal components.  This is measurable 
by comparing the cal gas analysis through both sample ports.  When the converter effectiveness is no longer 
acceptable, a replacement chamber may be installed. 

Complete a full shutdown sequence and include enough time for adequate cool down.  The canister starts at 
over 1250°F and is well insulated, so cool down may take up to 24 hours.  Pumping instrument air through the 
canister will reduce cool down time.   

1.  Unbuckle the ceramic heater/insulator strap and open the front half of the unit.  There should be 

adequate room to leave the heater wired up and still perform the swap.   

2.  Slide the thermocouple down and out of the canister.   
3.  Loosen the fittings from the canister tubes at the bulkhead wall and remove the canister. 

It is not recommended to perform maintenance on any other part of the converter assembly. 

 

 

Summary of Contents for Universal Analyzers 270SF

Page 1: ...5200 Convair Drive Carson City NV 89706 1 775 883 2500 sales universal ametek com www universalanalyzers com Model 270SF Gas Sample Probe with NH3 Convertor Instruction Manual...

Page 2: ...Symbols 4 3 0 Product Identification Configuration 5 4 0 Specifications 6 5 0 Description and Principle of Operation 7 6 0 Installation 9 7 0 Start Up 10 8 0 Shutdown 11 9 0 Maintenance 12 10 0 Troubl...

Page 3: ...cessories immediately on arrival by removing them from the packing and checking for missing articles against the packing list Check the items for any damage which may have occurred during transit and...

Page 4: ...ES EXPOSED SURFACE TEMPERATURE CAN CAUSE BURNS OR PERSONAL INJURY CARE SHOULD BE TAKEN WHEN CONTACT IS REQUIRED CAUTION RISK OF ELECTRICAL SHOCK SYMBOL INDICATES ELECTRICAL SHOCK MAY OCCUR CAUTION SHO...

Page 5: ...e current version of all Model 270SF with Ammonia Convertor product configuration visit the Universal Analyzers website https www universalanalyzers com Navigate to Products Gas Sample Probes Model 27...

Page 6: ...uggested Blowback Timer Period Controlled externally Blowback Solenoid Valve Voltage As specified Maximum NH3 Concentration 20 ppm by volume MATERIALSPECIFICATIONS Enclosure Sample Probe Fiberglass or...

Page 7: ...provided as a means to measure and transmit or record the temperature of the filter A second thermal switch set at 225 F 105 C is provided to be used as an alarm contact if the temperature drops belo...

Page 8: ...lve set to approximately 3 psi is provided in the cal gas injection path to ensure that the gas does not leak into the sample path during normal operation After the filter cal gas is drawn through bot...

Page 9: ...the check valve on the side of the chamber The blowback instrument air tubing connects to the fitting close to the accumulator sphere If an external air line is to be utilized use a bulkhead fitting i...

Page 10: ...r should be installed in the cal gas supply line to ensure that at least 10 more gas is being supplied than what is withdrawn as sample This calculation should include the sum of the unconverted and c...

Page 11: ...ed to temperatures above 300 F and can cause serious burns 4 For further disassembly shut down all heaters in the probe and converter 5 It is recommended to flow instrument air through the converter f...

Page 12: ...r end of the filter Screw the cap back on the filter body The filter replacement procedure is complete NH3 CONVERTER The NH3 Converter requires relatively little maintenance but over a long period of...

Page 13: ...unit Check by measuring for AC voltage on TB1 1 2 Verify by measuring for a closed circuit between TB1 1 4 High oxygen readings low pollutant readings Leak Leaking past the filter cap O ring Remove fi...

Page 14: ...l 270SF with Ammonia Convertor drawings and spare parts visit the Universal Analyzers website https www universalanalyzers com Navigate to Products Gas Sample Probes Model 270SF w NH3 Links to all cur...

Page 15: ...y charge late payment fees at the rate of 1 5 per month or the highest rate permitted by law whichever is less accruing daily B If the financial condition of Buyer is unsatisfactory to Seller Seller m...

Page 16: ...or otherwise THE FOREGOING WARRANTIES ARE IN LIEU OF ALL OTHER WARRANTIES WHETHER ORAL WRITTEN EXPRESS IMPLIED OR STATUTORY NO IMPLIED OR STATUTORY WARRANTIES OF MERCHANTABILITY OR FITNESS FOR PARTICU...

Page 17: ...persede any prior or contemporaneous representations agreements proposals warranties or understandings oral or written express or implied No waiver modification amendment rescission or other change to...

Reviews: