J. PREOPERATIONAL TESTS
ALL
dryers are thoroughly tested and inspected before leaving the factory. However, a preoperational test
should be
performed before the dryer is publicly used. It is possible that adjustments have changed in transit or
due to marginal location (installation) conditions.
1. Turn on electric power to the dryer.
2. Make sure the main door is closed and the lint drawer is securely in place.
3. Refer to the Operating Instructions for starting your particular model dryer.
4. Check to ensure that the basket (tumbler) starts in the clockwise (CW) direction. Additionally, check the
direction of the blower motor impellor (fan) to ensure that the impellor (fan) rotates in the clockwise (CW)
direction as viewed from the front. If it is, the phasing is correct. If the phasing is incorrect, reverse two
(2) of the leads at L1, L2, or L3 of the power supply connections made to the dryer.
IMPORTANT:
Dryer blower motor/pulley that drives the impellor/fan (squirrel cage) when viewed
from the back of the dryer
must turn
in the counterclockwise (CCW) direction,
otherwise the dryer efficiency
will be
drastically reduced and premature component
failure can result.
5. Heat Circuit Operational Test
a. Gas Models
1) When the dryer is first started (during initial start-up), the burner has a tendency not to ignite on the
first attempt. This is because the gas supply piping is filled with air, so it may take a few minutes for
this air to be purged from the lines.
2) The dryer is equipped with a Direct Spark Ignition (DSI) system, which has internal diagnostics. If
ignition is not established after three (3) attempts, the heat circuit DSI module will LOCKOUT until
it is manually reset. To reset the DSI system, open and close the main door and restart the dryer
(press the “START” key).
NOTE:
During the purging period, check to be sure that
ALL
gas shutoff valves are open.
3) Once ignition is established, a gas pressure test
should be
taken at the gas valve pressure tap of
each dryer to ensure that the water column (W.C.) pressure is correct and consistent.
NOTE:
Water column pressure requirements (measured at the gas valve pressure tap):
Natural Gas ________________ 3.5 Inches (8.7 mb) Water Column.
Liquid Propane (L.P.) Gas _____ 10.5 Inches (26.1 mb) Water Column.