The R30K low voltage control can be mounted directly to a fi nished wall either inside or outside the steam room. The 

R30K does not control the temperature in the steam room. 

1. Use a 1-1/2” (36 mm) hole saw to drill a hole in the fi nished steam room wall where the control is to be mounted (the

    control cable should already be roughed-in to this location). 

2. Locate the control cable, pull it out through the mounting hole and plug it into the connector on the back of the control 

    board, inside the housing. 

3. Run a bead of 100% silicone caulk around the perimeter on the back of the control housing. Insert the control into the 

    wall cavity. Tape the control in place until the silicone has set.

4. Route the R30K control's cable to the steamer circuit board and plug it in to the S30B jack (top edge of the circuit board

    next to the S30A terminal block).

  

SECTION 2: INSTALLATION OF THE R30K: 

2017 and later AK Generators

The steam generator, steam head, fi ttings and plumbing connections should be inspected at least annually for water leaks 

and damage.

The AK steam generator is supplied with a drain valve for fl ushing sediments from the generator tank.  This procedure 

should be scheduled monthly or more often depending on local water conditions and steam bath usage.

FLUSHING PROCEDURE

1. The generator should be cool.

2. Turn control on.

3. Open the drain valve.

4. The unit will drain without heating the water.

5. Allow the water to run 10 minutes.

6. Close the drain valve

  

SECTION 3: MAINTENANCE OF THE AK SERIES

W-D COM

DRAIN

WATER

SVC

S30B

J4

S30A

S60 A

S60 B

1

2

3

H

R

L

G1

G2

AK IN

R30K

1-

1

/

2

" (36 mm) HOLE

SILICONE

BACKSIDE

New model AK generators have their circuit boards mounted on the back panel of the generators. Earlier AK and 3K gen-

erators have their circuit boards mounted on the generator's shelf. 

All operations of both versions are otherwise identical.

For installation in an older steam generator, install the R30K same as in steps 1 - 3 in the new AK Instructions above then"

4. Route the R30K control's cable to the steamer circuit board and plug it in to the S30B jack (near center on the right 

end of the circuit board).

  

SECTION 2: INSTALLATION OF THE R30K: 

AK & 3K Generators Built Before March, 2017