24
Assembly for 1450 Towers
Assembly Procedure - Mobile Towers 1450 3T Method
8.
Continue to add pairs of end frames, diagonal braces and fit trapdoor decks as shown in the
previous steps. At every platform level, add horizontal braces as guardrails at 2 and 4 rungs above
the platform.
Fit these guardrail braces from the protected trapdoor position. Do not climb onto the platform
until it is fully guardrailed.
Continue until the required height is reached. Re-position the fixed deck to the required platform
height and fit a trapdoor deck alongside it as shown in
Stage 7
. Fir a single diagonal at the top
of the tower as shown in
Stage 7
. Fit the guardrails as shown in
Stage 7
.
Assembly for 1450 Towers
Assembly Procedure - Mobile Towers 1450 3T Method