Assembly and Dismantling Procedures
To Dismantle A BoSS Ladderspan Tower
Assembly Procedure - Mobile Towers - 3T Method
•
To comply with the Work at Height Regulations we show assembly procedures with platforms
every 2 metres in height, and, the locating of guardrails in advance of climbing onto a platform to
reduce the risk of a fall.
•
All platforms feature double guardrails on both faces of either individual platforms or fully
decked levels.
•
All guardrails should be 2 and 4 rungs (0.5m and 1.0m) above platforms.
•
Never stand on an unguarded platform positioned above the first rung of a tower. If your risk
assessment shows it necessary, you may also need to guardrail platforms at this level.
• Always start building with the smallest height frames at the base of the tower:
•
Remove toeboards, and pass down the tower.
•
Unclip farthest end of braces and immediately go to protected trapdoor position on ladder to
complete removal.
•
Remove upper platforms from protected platform levels below.
•
Pass removed components out of the tower to a colleague.
Where all 3 frame heights are used in a tower, start with 4 rung frames at the base, with the 6
rung frames next and the 8 rung frames on the top. Refer to the quantity schedules for detail.
Platform Height In Metres
Frame At Base
1.7, 2.2, 3.7, 4.2, 5.7, 6.2, 7.7, 8.2, 9.7, 10.2, 11.7, 12.2
2 rung
2.7, 4.7, 6.7, 8.7, 10.7
3 rung
1.2, 3.2, 5.2, 7.2, 9.2, 11.2
4 rung