Pull in the cables and conductors and make
the connections
1. Strip the sheathing of all cables to the external
loads before laying in the cable duct of the control
box.
2. Open electrical switchbox:
●
Undo 4 screws in the cover panel of the electri-
cal control box
●
Remove the cover panel
3. Feed the control/sensor cables and unit supply
cable into the housing from the rear.
4. Route cables from underneath through the cable
openings in the control box.
5. Connect cables to the respective terminals
(
“Terminal diagrams”, from page 40).
Operate the controller via a PC /network
1.
During installation lay a shielded network cable
(category 6) through the unit.
2.
Plug the RJ-45 connector of the network cable
into the socket of the control unit
(①)
.
1
NOTE
The network cable can be retrofitted at any
time.
6.5 Installing the control panel
NOTE
The control can be inserted in a recess in the
front panel of the unit or can be installed on
the wall.
Insert the control in the unit and connect
1.
If required: Remove masking plate from the slot.
To do this, dismantle the front panel (
“Dismantle
housing panels for transport with handcart or
carrying the unit”, page 10), press the lugs
together and push out of the openings.
2.
Remove film from the plastic element of the front
panel.
3. Position the control in the recess in the front unit
panel.
4. Cut the cable to length generously so that the
front panel can be removed and placed to the side
of the unit. Do not cut the cable ties for strain relief
of the LIN bus cable at the electric control box.
● LIN bus cable approx. 1.1 m from the fixing of
the strain relief at the electrical control box
●
All other cables approx. 1.2 m