17
Subject to technical amendments without prior notice | 83070000cUK | ait-deutschland GmbH
If the heating circuit is filled with anti-freeze, and de-
pending on the concentration of the mixture, the fol-
lowing points must be observed:
●
The heating capacity of the heat pump is reduced
●
The COP value becomes worse
●
The output of circulation pumps used on site is re-
duced, and the specified free compression for in-
tegrated circulation pumps decreases
●
You must ensure the materials in the components
used are compatible with the anti-freeze mixture
Hydraulic tower HT 7 operating manual
10 Insulating hydraulic
connections
Insulate hydraulic lines in accordance with local regu-
lations.
1. Open shut-off devices.
2. Perform a pressure test and check for leaks.
3. Insulate external piping on site.
4. Insulate all connections, fittings and pipes.
5. Insulate the condensate drain to ensure protec-
tion against frost.
6. Enclose the unit completely to ensure protection
against rodents.
7. Protect hydraulic and electrical cables on site
against rodents.
IMPORTANT
When using the accessories CPS, make the hydrau-
lic insulation UV-resistant on site.
IMPORTANT
When using the accessories HVLD, seal the transi-
tion to the KG pipe with the end cover EDH 32/160
(accessories).
11 Overflow valve
Hydraulic tower HT 7 operating manual
12 Commissioning
WARNING
The unit may only be put into operation
with mounted façades and fan protective
grilles.
Relevant planning & design data of the system
must be documented in full
The relevant energy supplier must be notified that
the heat pump system is in operation
The system must be air-free
An installation check using the general checklist
must be completed successfully
The right-hand (clockwise) rotating load infeed
field must be available at the compressor (only
applies to units with 400V connection)
The system must be set up and installed accord-
ing to this operating manual.
The electrical installation must be carried out
properly according to this operating manual and
local regulations
The power supply for the heat pump must be
equipped with an all-pole circuit breaker with at
least 3 mm contact spacing (IEC 60947-2)
The level of the tripping current must be main-
tained
The heating circuit must be flushed and vented
All shut-off devices in the heating circuit must be
open
The pipe systems and components of the system
must be leak-tight
The heat pump must be addressed as "Slave 1" in
the heating and heat pump controller.
Commissioning Jersey 5
1. Supply Jersey 5 and hydraulic tower HT 7 with
power.
2. Follow the instructions for commissioning in the
heating and heat pump controller HPC operating
manual.
Heating and heat pump controller HPC operating
manual