background image

8

9

Ground System Configurations

A ground resistance of less than 10

 is required for proper operation of the 

TerraStreamer

®

 ESE Terminal. If, due to space constraints or high soil resistivity, 

it is not possible to readily install a grounding system as recommended, 

alternate grounding methods and designs shall be considered. 

In order to meet safety and grounding system resistance requirements, Alltec 

recommends the installation of a purpose designed and installed grounding 

system such as the radial (crow’s foot) design or Delta design. Other 

configurations and materials are allowed, and may be required due to local 

conditions.

NOTE: Alternate grounding methods and designs are allowed by NF C 

17-102, and Alltec is capable of designing a grounding system to meet 

specific resistance goal in any type of soil.

D

D

P

P

B

B

D: Down-conductor
B: Building foundation loop ground
P: Grounding system

Radial

Delta

Fig. B 

- Recommended Grounding Configurations

1.  Installation of the Grounding System

 

‰

Each radial should consist of a trench (approx. 50cm deep x 20cm wide x 

10m length).

 

‰

A ground rod should be driven at the end of each radial. 

 

‰

The use of copper conductor is recommended, with a cross sectional area 
of not less than 50mm². Tin-plated copper is recommended for its corrosion 

resistance.

 

‰

All rods should be interconnected through the use of 1/0-19 strand bare 
conductor and ground rod clamps or TerraWeld® exothermic welding. The 
use of the TerraWeld® exothermic welding process is a safe and efficient 

way of providing a permanent connection between conductors. TerraWeld® 
connections will not rust or corrode over time.

 

‰

ESE Grounding Systems should utilize TerraDyne® Electrolytic Ground 
Electrodes and TerraFill® ground enhancement backfill to provide the 
desired low resistance ground system and stabilize low contact resistance 
at locations where the native soil has relatively high resistivity, low ground 

Summary of Contents for TerraStreamer TPV-60

Page 1: ...TerraStreamer Early Streamer Emission Terminals Installation Instruction Guide MODELS TSP 20 TSP 30 TSP 40 TSP 50 TSP 60 TPV 60...

Page 2: ...aStreamer ESE Post Installation Verification 18 7 Inspection Maintenance 18 Schedule 18 Checklist 18 Disclaimer 19 Warranty The warranty is limited to the cost of replacement of equipment providing it...

Page 3: ...protection system can provide 100 protection from lightning We refer to the French Standard NF C 17 102 As in the case with anything related to the natural elements a lightning protection system desig...

Page 4: ...eld which is present with approaching thunderstorms and become active only during storm activity The system operates without the need for external power supply or spare parts for standard operation To...

Page 5: ...20 25 30 32 3 24 30 37 44 48 4 31 40 50 59 63 5 39 50 62 73 79 6 40 50 62 74 79 8 40 51 63 74 79 10 41 51 63 74 80 Level II 2 18 23 28 32 35 3 27 35 42 48 52 4 36 47 55 64 70 5 45 58 69 80 87 6 47 58...

Page 6: ...mping sites etc they should be installed on specific supports such as tower mast lightning poles pylons or any other nearby structures which enable the ESE Terminal to cover the area to be protected T...

Page 7: ...r to connection to the grounding system or immediate connection is not possible connect the lower end of the down conductor to structural steel reinforcing or other suitable grounding point Before ins...

Page 8: ...undation loop ground P Grounding system Radial Delta Fig B Recommended Grounding Configurations 1 Installation of the Grounding System Each radial should consist of a trench approx 50cm deep x 20cm wi...

Page 9: ...lowed NF C 17 102 requirements should be strictly adhered to as regards materials and design requirements for number and placement of TerraStreamer ESE Terminals and down conductors The route of the d...

Page 10: ...SE terminals are located on the same building the down conductors shall be mutualized on a case by case basis but a minimum of one down conductor is mandatory for each ESE terminal When a natural comp...

Page 11: ...d radius is maintained never less than 20 cm DO NOT double the down conductor back against itself after changes of direction i e 180 bend The down conductor should be installed as close flush as possi...

Page 12: ...stem through the use of a suitable ground rod clamp or by using TerraWeld exothermic welding Exterior Wall 1m Minimum Ground Rod Clamp or Exothermic Weld Ground Rod Minimum 16mm Diameter x 3m length 5...

Page 13: ...strip Round stranded copper wire is inserted into the hole in the base of the adaptor and secured with the two screws provided Flat copper strip attaches to the external flat side of the adaptor Terra...

Page 14: ...priate safety railings It is very important to keep the mast straight during the lift to avoid damaging the mast The TerraStreamer ESE Terminal must NOT be used as a slinging point When lifting masts...

Page 15: ...ESE Terminal Strike Counter Inspection Well Grounding System FRP Mast Mast Base Guy Ring Guy Wire Fig H Mid Roof location TerraStreamer ESE Terminal Strike Counter Inspection Well Grounding System FR...

Page 16: ...cal point somewhere along the length of the mast Particular care should be taken to ensure that compatible metals are used when connecting the down conductor to metallic masts e g aluminum to copper c...

Page 17: ...ion along the down conductor length where it can be accessed easily for inspection Typically the strike counter should be installed approximately 2m from ground level The strike counter should be moun...

Page 18: ...tenance Alltec recommends inspection and any required maintenance to be performed regularly and as listed below Schedule After each known lightning strike to the terminal Once every twelve months mini...

Page 19: ...SE Terminal nor any other lightning protection system to our knowledge can provide 100 protection from lightning In order to provide the most effective Early Streamer Emission ESE Air Terminal technol...

Page 20: ...www alltecglobal com WORLD HEADQUARTERS 64 Catalyst Drive Canton North Carolina 28716 USA TEL 1 828 646 9290 FAX 1 828 412 4270 EMAIL info alltecglobal com 2017 ALLTEC 420 001 11 22 2017...

Reviews: