6. TerraStreamer
®
ESE Post Installation Verification
The following should be checked for quality of workmanship and compliance to
recommended installation instructions, approved design documents, and NF C
17-102/UNE 21 186 requirements:
Correct TerraStreamer
®
ESE Terminal model and placement for proper
zone of protection (verify model, height above structures, and radius of
protection).
Correct mast and any associated brackets and fasteners have been used
for installation.
Guying, anchor points and fastenings (if applicable).
Down conductor size, routing, and attachment points
Connection of down conductor to grounding system
Grounding system (3-Point resistance test to verify 10 Ohms or less)
Lightning Strike Counter installation is per recommended guidelines. Record
“strike count” for later comparison.
Safety and product labeling
7. Inspection/Maintenance
Alltec recommends inspection and any required maintenance to be performed
regularly and as listed below:
Schedule
•
After each known lightning strike to the terminal.
• Once every twelve months minimum.
• If changes have been made to the protected structure.
Checklist
Check Lightning Strike Counter “strike count”, and compare to previous
display number.
Check Lightning Strike Counter installation for missing/damaged wires and
connections.
Check the strike counter for secure installation and record the number of
strikes, if any.
Check for any damage to the TerraStreamer® ESE down-conductor and
grounding system.
Check TerraStreamer® ESE Terminal body and tip for excessive pitting or
other damage.
Inspect the TerraStreamer® ESE Terminal and ensure that no dirt or
other matter is embedded in the air gap between the center tip and the
surrounding panel edges.
Verify that the structure to be protected has not been modified or expanded
since the last maintenance check.
Make sure that the electrical continuity of all visible conductors is correct,