507277-02
Page 9 of 52
Issue 1621
INSTALLATION – Setting Equipment
Select a location that allows for the required clearances that
are listed on the unit nameplate. Also consider gas supply
connections, electrical supply, vent connection, condensate
trap and drain connections, and installation and service
clearances [24 inches (610 mm) at unit front]. The unit must
be level from side to side. Tilt the unit slightly (maximum
1/2 in. from level) from back to front to aid in the draining of
the heat exchanger. See Figure 11.
Shipping Bolt Removal
NOTE:
Units with a 1/2 hp & 3/4 hp blower motors are
equipped with three flexible legs and one rigid leg. The
rigid leg is equipped with a shipping bolt and a flat white
plastic washer (rather than the rubber mounting grommet
used with a flexible mounting leg). See Figure 10.
The
bolt and washer must be removed before the furnace
is placed into operation.
After the bolt and washer have
been removed, the rigid leg will not touch the blower housing.
NOTE:
These units may be equipped with a shipping pad
under the blower housing. Remove the shipping pad prior
to operation.
Allow for clearances to combustible materials as indicated
on the unit nameplate. Minimum clearances for closet or
alcove installations are shown in Figure 13.
Figure 11
Setting Equipment
FRONT VIEW
SIDE VIEW
AIR FLOW
AIR FLOW
1/2"
max.
AIR FLOW
SIDE VIEW
Unit must be level side−to−side. Unit may be positioned
from level to 1/2" toward the front to aid in draining.
Figure 10
Units with 1/2 HP & 3/4 HP
Blower Motor
Figure 12
Figure 9
Equipment in Confined Space
WARNING
Blower access panel must be securely in place when
blower and burners are operating. Gas fumes, which
could contain carbon monoxide, can be drawn into living
space resulting in personal injury or death.
WARNING
Do not install the furnace on its front, back or in the
horizontal position. See Figure 12. Do no connect the
return air ducts to the back of the furnace. Doing so
will adversely affect the operation of the safety control
devices, which could result in personal injury or death.
Summary of Contents for 95G1DFE
Page 29: ...507277 02 Page 29 of 52 Issue 1621 Figure 43 Trap Drain Assembly Using 1 2 PVC or 3 4 PVC ...
Page 35: ...507277 02 Page 35 of 52 Issue 1621 Typical Wiring Diagram Figure 50 For A95DF1E 95G1DFE ...
Page 46: ...507277 02 Page 46 of 52 Issue 1621 Troubleshooting Heating Sequence of Operation ...
Page 47: ...507277 02 Page 47 of 52 Issue 1621 Troubleshooting Heating Sequence of Operation continued ...
Page 48: ...507277 02 Page 48 of 52 Issue 1621 Troubleshooting Cooling Sequence of Operation ...
Page 49: ...507277 02 Page 49 of 52 Issue 1621 Troubleshooting Continuous Fan Sequence of Operation ...