SwitchBlade x8106 Chassis Switch and AT-SBx81CFC400 Card Installation Guide
93
2. Lift the AT-SBx8106 Chassis into the equipment rack and set the
bottom of the equipment rack brackets firmly on the two equipment
rack screws you installed in “Preparing the Equipment Rack” on
page 83, as shown in Figure 33.
Figure 33. Lifting the AT-SBx8106 Chassis into the Equipment Rack
3. With the bottom of the rack mount ears resting on the two rack mount
screws, tilt the top of the chassis back until both rackmount brackets
are flush and parallel with the vertical rack rails.
4. Install four rack mount screws (not provided) to secure the chassis to
the equipment rack, as shown in Figure 34 on page 94.
Summary of Contents for AT-SBx8
Page 8: ...Contents 8...
Page 12: ...List of Figures 12...
Page 14: ...List of Tables 14...
Page 18: ...Preface 18...
Page 32: ...Chapter 1 Chassis and Power Supplies 32...
Page 118: ...Chapter 6 Installing the Power Supplies 118...
Page 134: ...Chapter 7 Installing the AT SBx81CFC400 Controller and Ethernet Line Cards 134...
Page 152: ...Chapter 8 Installing the Transceivers and Cabling the Ports 152...
Page 190: ...Chapter 9 Powering On the Chassis 190...
Page 212: ...Chapter 11 Troubleshooting 212...