Commissioning Procedures
1. Bake open gas valve and check machine for
leaks.
2. Purge moisture out of machine. Refer to
Purging
Moisture
.
Purging Moisture
At the first heating of the machine, air a moisture must
be purged out of the system. To do this:
1. Take off existing hose. Do not throw away. Refer
.
2. Connect the teflon hose provided on top of the
machine in its place.
3. Heat the machine fully.
4. Place one end of the teflon hose into a tub. Refer
.
5. Let teflon hose drain into tub.
6. Remove the teflon hose.
7. Replace original hose.