© Copyright, Alliance Laundry Systems LLC – DO NOT COPY or TRANSMIT
512042
10
NOTE: When connecting to a gas line, an
equipment shut-off valve must be installed within
6 feet (1.8 m) of the dryer. An 1/8 in. NPT pipe plug
must be installed as shown for checking inlet
pressure. Refer to Figure 5.
Figure 5
4. Tighten all connections securely. Turn on gas and
check all pipe connections (internal & external)
for gas leaks with a non-corrosive leak detection
fluid.
NOTE: The dryer and its appliance main gas valve
must be disconnected from the gas supply piping
system during any pressure testing of that system
at test pressures in excess of 1/2 psi (3.45 kPa).
Refer to Step 9 (Check Heat Source).
L.P. (Liquefied Petroleum) Gas
, 2500 Btu/ft
3
(93.1 MJ/m
3
) service must be supplied at 10 ± 1.5 inch
water column pressure.
For proper operation at altitudes above 3000 feet (915 m)
the L.P. gas valve spud orifice size must be reduced to
ensure complete combustion. Refer to
.
NOTE: DO NOT connect the dryer to L.P. Gas
Service without converting the gas valve. Install
L.P. Gas Conversion Kit 649P3, available at extra
cost.
D434I
1
New Stainless Steel Flexible Connector – Use
only if allowed by local codes (Use Design
A.G.A. Certified Connector)
4
Black Iron Pipe
Shorter than 20 ft. (6.1 m) – Use 3/8 in. pipe
Longer than 20 ft. (6.1 m) – Use 1/2 in. pipe
2
1/8 in. N.P.T. Pipe Plug
(for checking inlet gas pressure)
5
3/8 in. N.P.T. Gas Connection
3
Equipment Shut-Off Valve – Installed within 6 ft.
(1.8 m) of dryer
1
2
3
4
5
L.P. Altitude Adjustments
Altitude
Orifice Size
Part No.
feet
m
No.
inches
mm
3000
915
55
0.0520
1.32
58755
8000
2440
56
0.0465
1.18
503786
Table 3
Summary of Contents for 512042R4
Page 19: ......