Installation
Elbow
To make it easier to disconnect the heat exchanger, an elbow should be fitted to the connection
in the pressure plate, directed upwards or sideways, and with another flange located just outside
the contour of the heat exchanger.
Shut-off valve
To be able to open the heat exchanger, shut-off valves should be provided in all connections.
Connection
Different types of connections can be used to connect the piping system to the apparatus.
Flanged connections shall be attached with pin bolts.
Avoid excessive loads from the piping system.
Connections in the pressure plate
It is important that the plate pack has been tightened to the correct dimension
A
(check against
the PHE drawing) before the piping system is connected.
When opening the heat exchanger, the pressure plate must be moved. Do not use fixed pipes or
other parts like feet, fasteners etc. inside the shaded area.
Drip tray (optional)
Depending on the type of fluid in the heat exchanger and the type of installation, a drip tray
(drainage box) may be necessary to avoid injury to personnel and damage to equipment.
Note!
Put the drip tray in place before positioning the heat exchanger.