7
Installation
3.
If the pump does not deliver after
10–15 seconds of operation, abort initial
commissioning, establish the cause of
the fault and only then continue the
commissioning procedure. Follow the
instructions in the fault table, see
4.2
Troubleshooting on page 19
.
4.
Run the pump for a few minutes to allow the
pipe system to vent fully. The pipe system
is fully vented when there is a smooth
operating noise and a pressure gauge on
the pressure side of the pump shows no
more fluctuations.
7.6.4
Taking the pump out of
operation
!
WARN
ING
Risk of injury or poisoning through emitted
pumped liquid.
Wear protective clothing during all the work.
Collect the emitted pumped liquid safely and dispose
of it in an environmentally compatible manner.
Carry out the following measures during shutdowns:
Pump is
Measure
shut down for longer period
Depending on pumped liquid, see below..
drained
Close the pressure-side and suction-side shut-off
devices.
dismantled
Disconnect the motor from the power supply and secure
it against being switched back on.
stored
Observe measures for storing and preservation, see
page
51
.
Measures for operation interruption
Behavior of the pumped
liquid
Duration of the shut down
Short
Long
sediment solids
Rinse the pump.
Rinse the pump.
congealed/frozen
Heat or drain the pump.
Drain the pump.
no corrosive burden
congealed/frozen
Heat or drain the pump.
Drain the pump.
corrosive burden
Preserve the pump.
remains liquid
—
—
47
Summary of Contents for ALP 15-85
Page 6: ... ...
Page 8: ...1 EC Declaration of Conformity ...
Page 10: ...2 Warning signs in text ...
Page 18: ...3 Function Description ...
Page 22: ...4 Fault Finding ...
Page 36: ...6 Technical Data 6 4 1 Dimension drawing of ALP pump and pump unit X027341A 36 ...