6 Installation
6.1 Installation Criteria
Only skilled professionals with experience installing rack-mounted electrical systems should
perform installation of the BOX. Persons installing the BOX should be able to lift 50 lbs.
without assistance. At least 2 people are required to install the BOX, 3 are recommended.
Installation instructions should be followed exactly; improper installation of the BOX could
void the warranty of the BOX and any or all its component parts.
If any instructions are unclear, or any additional information is required during the process,
please contact Alencon Systems LLC for assistance, see Appendix C.
6.1.1 Required Tools List:
Hammer Drill
Masonry Drill Bit (Appropriate size for customer supplied anchors)
Adjustable wrench
Power Driver with Socket Drive Adapter
Ratchet and Extensions
3/8” Socket
9/16” Socket
13mm Socket
#2 Phillips Screwdriver
3/16” Flathead Screwdriver
6.1.2 Customer Supplied Hardware:
Enclosure anchoring hardware (assumed concrete anchors listed below)
o
(4) ½” concrete anchor bolts with nuts and washers
Unistrut and Hardware to Mount PODD Enclosure
o
(2) 5/16” x ¾” L Bolts (or M8)
o
(2) 5/16” flat washers (or M8)
o
(2) 5/16” Unistrut nuts (or M8)
(1) Waterproof grommet or bulkhead for CAT cable with RJ-45 connectors
Zip-ties or Velcro tape for cable management