Power supply wiring
Tightening to torque for the terminal screws
Electrical characteristic
Specifications for field supplied ELB and wire
Mainbus and R/C communciation wiring
1.Unscrew and remove the service lid.
2.Connect the power supply wiring to the power supply
terminal block.
3.When doing this,press the power supply wiring under the
wire clip tightly.
1.Use the correct screwdriver for tightening the terminal screws.If the blade of screwdriver is too small, the head of the screw might be damaged, and the
screw will not be properly tightened.
2.If the terminal screws are tightened too hard, screws might be damage.
3.Refer to the table below for the tightening torque of the terminal screws.
1.Unscrew and remove the service lid.
2.Connect the R/C wirings to R1,R2 terminal block and the
mainbus wirings to F1,F2 terminal block.
3.Press the wirings under the wire clip tightly.
Terminal
Size
Tightening torque
Remote controller, Transmission wiring and forced offterminal block(4P)
M3.5
0.8~1.0N.m
Power supply and Ground terminal block(3P)
M4
1.2~1.5N.m
Unit
Power supply
Fan motor
Model
Hz
Volts
MCA
MFA
KW
FLA
LEV22
50
220~240
0.23
16
0.02
0.06
LEV28
0.23
16
0.02
0.06
LEV36
0.23
16
0.02
0.06
LEV45
0.23
16
0.02
0.07
LEV56
0.23
16
0.02
0.07
LEV63
0.23
16
0.02
0.07
MCA : Min. Circuit Amps (A)
MFA : Max. Fuse Amps(A)
KW : Fan Motor Rated output(KW)
FLA : Full Load Amps(A)
Model
Power supply wiring
Remote controller wiring
communication wiring
PNV007
Field ELB
Wire and Size
Wire
Size
PNV009
16A
Must comply
with maximum
current and local
codes(≥0.75mm
2
)
Twisted-
pairwires
≥1.0mm
2
PNV012
PNV015
PNV018
PNV021
All field supplied parts and materials and electrics works must
conform to local codes.
Use copper wire only.
All wiring must be performed by an authorized electrician.
Every indoor unit must have a sub circle breaker and the whole
system must have a main circle breaker.
Be sure to ground the air conditioner.
The appliance shall be installed in accordance with national
wiring regulations, and shall be provided to ensure all-pole
disconnection from the supply mains, and distance between the
poles shall be more than 3 mm .
CHECK ITEMS
BEFORE POWER ON
�
Is there any gas leakage at flare nut connections?
�
Has the heat insulation been carried out at flare nut connection?
�
Is the connecting cable being fixed to terminal board firmly? Is the
connecting cable being clamped firmly?
�
Is the drainage ok?
�
(Refer to "Check the drainage" section)
�
Is the earth wire connection properly done?
�
Is the indoor unit properly hooked to the installation plate?
�
Is the power supply voltage complied with rated value?
AFTER POWER ON
�
Is there any abnormal sound?
�
Is the cooling operation normal?
�
Is the thermostat operation normal?
�
Is the remote control's LCD operation normal?
NOTE: For the piping and wiring methods,leakage test,vacuum process and installation setting
through HMI, please refter to “Outdoor unit Installation Manual”.
NOTE: For how to connect the power wire and communication wire between outdoor unit and indoor units, please refer to
chapter 9 “Field Wiring” in outdoor unit installation manual.