background image

Power supply wiring

Tightening to torque for the terminal screws

Electrical characteristic

Specifications for field supplied ELB and wire

Mainbus and R/C communciation wiring

1.Unscrew and remove the service lid.

2.Connect the power supply wiring to the power supply 

terminal block.

3.When doing this,press the power supply wiring under the 

wire clip tightly.

1.Use the correct screwdriver for tightening the terminal screws.If the blade of screwdriver is too small, the head of the screw might be damaged, and the 

screw will not be properly tightened.

2.If the terminal screws are tightened too hard, screws might be damage.

3.Refer to the table below for the tightening torque of the terminal screws.

1.Unscrew and remove the service lid.

2.Connect the R/C wirings to R1,R2 terminal block and the 

mainbus wirings to F1,F2 terminal block.

3.Press the wirings under the wire clip tightly.

Terminal

Size

Tightening torque

Remote controller, Transmission wiring and forced offterminal block(4P)

M3.5

0.8~1.0N.m

Power supply and Ground terminal block(3P)

M4

1.2~1.5N.m

Unit

Power supply

Fan motor

Model

Hz

Volts

MCA

MFA

KW

FLA

LEV22

50

220~240

0.23

16

0.02

0.06

LEV28

0.23

16

0.02

0.06

LEV36

0.23

16

0.02

0.06

LEV45

0.23

16

0.02

0.07

LEV56

0.23

16

0.02

0.07

LEV63

0.23

16

0.02

0.07

MCA : Min. Circuit Amps (A)

MFA  : Max. Fuse Amps(A)

KW  : Fan Motor Rated output(KW) 

FLA  : Full Load Amps(A)

Model

Power supply wiring

Remote controller wiring

communication wiring

PNV007

Field ELB

Wire and Size

Wire

Size

PNV009

16A

Must comply

with maximum

current and local

codes(≥0.75mm

2

 )

 Twisted-

pairwires

≥1.0mm

2

PNV012
PNV015
PNV018
PNV021

All field supplied parts and materials and electrics works must 

 

‰

conform to local codes.

Use copper wire only.

 

‰

All wiring must be performed by an authorized electrician.

 

‰

Every indoor unit must have a sub circle breaker and the whole 

 

‰

system must have a main circle breaker.

Be sure to ground the air conditioner.

 

‰

The appliance shall be installed in accordance with national 

 

‰

wiring  regulations,  and  shall  be  provided  to  ensure  all-pole 

disconnection from the supply mains, and distance between the 

poles shall be more than 3 mm .

CHECK ITEMS

BEFORE POWER ON

  Is there any gas leakage at flare nut connections?

  Has the heat insulation been carried out at flare nut connection?

  Is the connecting cable being fixed to terminal board firmly? Is the 

connecting cable being clamped firmly?

  Is the drainage ok?

  (Refer to "Check the drainage" section)

  Is the earth wire connection properly done?

  Is the indoor unit properly hooked to the installation plate? 

  Is the power supply voltage complied with rated value?

AFTER POWER ON

  Is there any abnormal sound?

  Is the cooling operation normal?

  Is the thermostat operation normal?

  Is the remote control's LCD operation normal?

     NOTE: For the piping and wiring methods,leakage test,vacuum process and installation setting 

                 through HMI, please refter to “Outdoor unit Installation Manual”.

NOTE: For how to connect the power wire and communication wire between outdoor unit and indoor units, please refer to 

                     chapter 9 “Field Wiring” in outdoor unit installation manual.