INSTALLATION DETAILS
DHK DCI 33 Version - 2
cylinder to the service port of the 3-way valve.
3). Air purging.
Open the valves on the charging cylinder and the
charge set. Purge the air by loosening the flare
nut on the 2-
way valve approximately 45’ for 3
seconds then closing it for 1 minute; repeat 3
times.
After purging the air, use a torque wrench to
tighten the flare nut on the 2-way valve.
4). Check the gas leakage.
Check the flare connections for gas leakage.
5). Discharge the refrigerant.
Close the valve on the charging cylinder and
discharge the refrigerant by loosening the flare
nut on the 2-
way valve approximately 45’ until the
gauge indicates 0.3 to 0.5 Mpa.
6). Disconnect the charge set and the charging
cylinder, and set the 2-way and 3-way valves to
the open position.
Be sure to use a hexagonal wrench to operate the
valve stems.
7). Mount the valve stems nuts and the service
port cap.
Be sure to use a torque wrench to tighten the
service port cap to a torque 18N
·
m.
Be sure to check the gas leakage.
8.4.3
Adding the refrigerant if the pipe
length >5m
Procedure:
1). Connect the charge hose to the charging
cylinder, open the 2-way valve and the 3-way
valve.
Connect
the
charge
hose
which
you
disconnected from the vacuum pump to the
valve at the bottom of the cylinder. If the
refrigerant is R410A, make the cylinder bottom
up to ensure the liquid charge.
2). Purge the air from the charge hose.
Open the valve at the bottom of the cylinder
and press the check valve on the charge set to
purge the air (be careful of the liquid
refrigerant).
3) Put the charging cylinder onto the electronic
scale and record the weight.
4) Operate the air conditioner at the cooling
mode.
5) Open the valves (Low side) on the charge set
and charge the system with liquid refrigerant.
6).When the electronic scale displays the proper
weight (refer to the table), disconnect the charge
hose from the 3-
way valve’s service port
immediately and turn off the air conditioner before
disconnecting the hose.
7). Mount the valve stem caps and the service
port
Use torque wrench to tighten the service port
cap to a torque of 18N.m.
Be sure to check for gas leakage.
8.5 Adding the refrigerant after running the
system for many years
Procedure:
1). Connect the charge hose to the 3-way service
port, open the 2-way valve and the 3-way valve.
Connect the charge hose to the valve at the
bottom of the cylinder. If the refrigerant is
R410A, make the cylinder bottom up to ensure
liquid charge.
2). Purge the air from the charge hose.
Open the valve at the bottom of the cylinder
and press the check valve on the charge set to
Summary of Contents for JSP060040
Page 12: ...DIMENSIONS Version 2 12 DHK DCI For JOSI DKH009 N11 For JOSI DKH012 N11...
Page 13: ...DIMENSION DHK DCI 13 Version 2 For JOSI DKH018 N11 For JOSI DKH024 N11...
Page 16: ...DIMENSIONS Version 2 16 DHK DCI...
Page 28: ...WIRING DIAGRAM Version 2 28 DHK DCI 7 3 Outdoor unit JOAU DKY018 H11...
Page 29: ...WIRING DIAGRAM DHK DCI 29 Version 2 7 4 Outdoor unit JOAU DKY024 H11...
Page 66: ...EXPLODED VIEW AND SPARE PART LIST Version 2 66 DKH DCI 12 2 JOSI DKH012 N11...
Page 68: ...EXPLODED VIEW AND SPARE PART LIST Version 2 68 DKH DCI 12 3 JOSI DKH018 N11...
Page 70: ...EXPLODED VIEW AND SPARE PART LIST Version 2 70 DKH DCI 12 4 JOSI DKH024 N11...
Page 72: ...EXPLODED VIEW AND SPARE PART LIST Version 2 72 DKH DCI 12 5 JOAU DKY009 H11...
Page 74: ...EXPLODED VIEW AND SPARE PART LIST Version 2 74 DKH DCI 12 6 JOAU DKY012 H11...
Page 76: ...EXPLODED VIEW AND SPARE PART LIST Version 2 76 DKH DCI 12 7 JOAU DKY018 H11...
Page 78: ...EXPLODED VIEW AND SPARE PART LIST Version 2 78 DKH DCI 12 8 JOAU DKY024 H11...
Page 80: ...SERVICE MANUAL DKH DCI Series...