Construction Materials

All ventilation components between the outlet of the ozone generator to and including the connection to the main 
exhaust duct must meet stainless steel specification AISI 304. Note: In grease exhaust applications it is common a 
stainless steel fire damper is installed in the connection appendage between the generator and main exhaust duct. 
Due to the potential for corrosion in this small section of duct, be sure to add regular inspections/replacement of any 
non-stainless components such as fusible links or sensors accompanying it (twice/year recommended) to the regular 
maintenance schedule for the facility.

Hanging the Generator

The ozone outlet pipe 

 6

 may have a maximum length of 15 ft. Its preferred diameter is 5 in. with a minimum diameter 

of 3 in.  Make sure that your installation does not block any inspection hatches or other equipment in the facility.

1.   Hang the ozone generator. 

 7

   

 

The ozone generator must always be suspended horizontally by its brackets with the service hatch facing downward. 

Never screw or drill through the generator. Hang using 5/16 in. threaded rods and anchor these with nuts on each 

side of the respective bracket. 

2.  Fasten the outlet pipe 

 6

 between the ozone generator 

 7

 and the eventual connecting point to the exhaust duct. 

3.  Connect the inlet pipe 

 8

 and IRIS air damper 

10

 to the ozone generator 

 7

, or use a filter box 

 9

 with a MERV5/

EU3 filter according to the pictures below.

 

Make sure that all connections are properly fastened and sealed.

TO HOOD 

OR DUCT

FILTER BOX INSTALLATION

CENTRAL AIR INSTALLATION

MERV5 / EU3 

FILTER BOXES

TO HOOD 

OR DUCT

IRIS DAMPERS

For Bleed Airflow rates, see section 2 “Planning Your Installation”

AirMaid

2000V/5000V

10000V

AirMaid

20000V

Note that the direction of the airflow 

 must correspond to the arrows on the generator and the pictures below.

Filtered air is required. On models with multiple pipes, you may manifold together supply and discharge pipes to single 

connections as long as the resulting installation complies with the product specification for bleed air through the 

generator. Remember to add filter inspection/replacement to the maintenance schedule. With central air installations, 

IRIS dampers are usually necessary for balancing purposes.

Summary of Contents for 10000V

Page 1: ...stallation Operation and Maintenance AirMaid V Series Ozone Cleaning System NORTH AMERICAN 120 VAC 2000V 5000V 10000V 20000V AirMaid ozone cleaning system Innovative Air Treatment Revised February 14...

Page 2: ...2...

Page 3: ...and extraction ducts must be installed by qualified per sonnel in compliance with all manufacturer instructions as well as local state and national building electric and fire safety codes Troubleshoo...

Page 4: ...generator 4 If the regular inspection and cleaning maintenance for the product are not followed 5 Any other damage resulting from accident alteration misuse if the serial number is removed or defaced...

Page 5: ...EU3 shall be in stalled Filter box inlet air can be taken from above an inner ceiling from an adjoining space or from the outdoors with precautions taken to prevent the entry of moisture If taken fro...

Page 6: ...e point of exhaust With this in mind we recommend a minimum dwell time of 2 seconds to obtain good results for the reduction of cooking odor However please keep in mind that a longer dwell time will o...

Page 7: ...THIS TYPICAL INSTALLATION DETAIL IS FOR REFERENCE ONLY THE PROJECT SPECIFIC INSTALLATION MUST MEET ALL LOCAL STATE AND NATIONAL BUILDING ELE CTRIC AND FIRE SAFETY CODES LAYOUT SHOWN IS COMPLIANT WITH...

Page 8: ...nlet and outlet pipes Multiple duct connections are unnecessary As long as you have sufficient static pressure to obtain the correct bleed airflow through the generator then multiple connections to th...

Page 9: ...ownward Never screw or drill through the generator Hang using 5 16 in threaded rods and anchor these with nuts on each side of the respective bracket 2 Fasten the outlet pipe 6 between the ozone gener...

Page 10: ...eir own alarm panel Electrical Connection The installation must be performed by an authorized electrician and follow national standards and regulations The fan interlock displayed on the diagram below...

Page 11: ...if you choose not to accept their factory defaults ALARM DELAY 5 minutes INSP CLEAN 12 months 4 Perform Functional Check Of CGC Cell s 4 1 Ensure the ventilation system of the facility is running norm...

Page 12: ...on with Interzon 7 1 Register the generator online within 10 days installation at www interzon com Registering the AirMaid generator installation is important to both the reseller and end customer Fir...

Page 13: ...em with the static pressure Kitchen hood filters might not be installed properly or a fire damper or control damper if installed is not open Perform troubleshooting following the flow chart in section...

Page 14: ...the delay is set to 5 minutes in order to prevent an alarm in case of a temporary disruption SET INSP CLEAN Service and maintenance interval in months After this time period the alarm panel will blin...

Page 15: ...if cleaning is performed before the timed reminder is displayed 1 Number of registered events 2 Cause A Alarm C Calibration P Pressure Fault N Not Connected generator not detected 3 Event Duration 4...

Page 16: ...the glass electrodes of the ozone cells are not damaged or cracked A proper ozone cell should be clean and free from any mechanical damage according to the picture to the right above Caution The glas...

Page 17: ...ired negative pressure is established The thermal switch prevents the ozone generator from overheating The main switch is supplied with a thermal overload protection of 4A Facts about Ozone Ozone is a...

Page 18: ...or Troubleshooting completed Turn off the main power switch and remove the service hatch on the bottom of the generator Are all electrodes of the CGC Cell s free from damage Please perform the steps i...