RECOMMENDED PERIODIC MAINTENANCE INTERVENTIONS TO UNITS WITH CENTRIFUGAL COMPRESSORS
DESCRIPTION
FREQUENCY
6 months
12 months
other
GENERAL CHECKS
Check that the compressor is not damaged
•
Check that there are no excessive vibrations induced by other operating components
•
CHECKS ON ELECTRICAL PARTS
Check the power supply voltage
•
Check the proper fastening of the compressor power supply cables
•
Check the good condition of the electrical cables
•
Check that the electric current value (A) is that specifi ed in the technical plate
•
Check the voltage value (A) on the storage tank capacitors
•
Replace the storage tank condensers
every 5 years
Check the correct functioning of the safety system (alarms)
•
CHECKS ON ELECTRONIC PARTS
Check that all communication cables between the compressor and its components
are fi rmly fastened
•
Check that all electronic devices are fi rmly in their seat
•
Visually check that the electronic boards are have no burns or are damaged
•
Check that the reading of the pressure/temperature sensors is correct
CHECKS ON THE COOLING CIRCUIT PARTS
Check the proper functioning of the thermostatic valve
•
Check the charge of refrigerant gas
(1)
•
Check the proper functioning of the solenoid valves
•
MAINTENANCE - LIST OF THE RECOMMENDED
PERIODIC INTERVENTIONS
DECOMMISSIONING AND DISPOSAL OF THE
MACHINE COMPONENTS
ATTENTION
The unit contains greenhouse eff ect fl uoride gases covered by
the Kyoto Protocol. The law prohibits its dispersion in the envi-
ronment and requires its recovery and delivery to the dealer or
collection centre.
When components are removed to be replaced or when the entire
unit reaches the end of its life and it must be removed from the
installation, in order to minimise the environmental impact, respect
the following disposal requirements:
• The refrigerant gas must be fully recovered in special containers
and brought to collection centres by specialised personnel
having the necessary qualification.
• The lubricating oil in the compressors and cooling circuit must
be recovered and brought to collection centres.
• The structure, electric and electronic equipment and
components must be separated according to their type and
construction material and brought to collection centres.
• If the water circuit contains mixtures with anti-freeze, the
content must be collected and brought to collection centres.
• Observe the current national laws.