background image

 

 

Step 3: Install the Collectors 
 

Refer to Figure 5 throughout this section 
 
Plan the collector location to allow at least one foot 
on all sides of the row(s) of collectors for mounting 
brackets and piping. 
 
Roof  obstructions,  if  present,  should  now  be  taken 
into account to determine the exact collector location. 
 
Collectors can be installed over or around different 
diameter roof vent pipes or other obstructions. After 
snapping the top chalk lines but before marking and 
pre-drilling for your outlet header brackets, refer to 
the following instructions: 
 
For roof vents up to 2” in diameter the collectors can 
be installed directly over these vents. Locate the seam 
in the panel nearest to where the vent pipe is to come 
through.  Separate  by  pulling  up  on  top  plate,  and 
pushing  down  on  the  lower  plate.  Should  the  vent 
pipe protrude near a sonic tack weld, it will have to be 
cut apart. Using a sharp utility knife, cut through the 
weld  while  pulling  the  two  plates  apart.  Lay  the 
collector over the vent pipe, keeping the vent pipe at 
least 12 inches away from a header. It will be easier to 
complete an installation by mounting this panel first 

then working away from it. With a roof vent pipe of 
3”  in  diameter,  the  collectors  can  be  positioned  on 
either side of the vent. Two 7” long hoses (60001-2) 
can be employed to couple the collectors together for 
vent pipes or other obstacles up to 7” in diameter… 
Mark  your  51”  centers  wherever  the  outlet  header 
brackets  ‘fall’  on  the  upper  chalk  line.  With 
obstructions  of  over  7”,  such  as  attic  fans  and 
skylights  lay  out  the  panels  on  either  side  of  the 
obstruction using a Row Spacer Kit Part No.  
18004-1. 

 

 
1.  Determine  the  position  of  the  last  outlet  header 
hold-down bracket for the row of collectors. Mark this 
point on the roof. The collector outlet header will be 
located  approximately  five  (5)  inches  below  this 
mark. Refer to Figure 6. 
2. Using this point, snap a chalk line to the opposite 
end of the row. This line should slope down the roof 

Summary of Contents for 16004-10

Page 1: ...oyment First you should thoroughly plan the proposed system before installation Section One of this manual explains and illustrates the required kits and components Section Two provides detailed instr...

Page 2: ...ordered separately Use one 1 kit for each collector 2 System Kit Part No 18002 1 Contains additional hold down hardware and connecting parts and adapters needed to complete water connection from the...

Page 3: ...Polypropylene fabric strap 5 8 wide 100 or 300 ft long 7 Header Inserts Part No 50055 1 are used in special situations where unusually high stagnation temperatures are expected such as in desert clima...

Page 4: ...installed in some cases Select appropriate pipe size for the system supplyand return lines The headers of the POLY PRO collectors are 2 and the pipe adapters included in the kits connect to 2 PVC Sch...

Page 5: ...sharp utility knife cut through the weld while pulling the two plates apart Lay the collector over the vent pipe keeping the vent pipe at least 12 inches away from a header It will be easier to compl...

Page 6: ...not install the hold down brackets until the collectors are in place 5 bring the first collector to the roof and slip the proper hoses over both end of the inlet and outlet headers on the last return...

Page 7: ...the vacuum relief valve in the outlet header of each row This will be located at the opposite end of the row that is connected to the collector outlet pipe Refer to Figures 4 and 12 12 Install an end...

Page 8: ...manufacturer s instructions included with the automatic equipment you use Other Equipment Some pools employ an automatic pool cleaner This should be plumbed before the control valve to assure positive...

Page 9: ...d one 1 Referring to the figure below locate the tube to be isolated End tube has been shown for clarity Using a sharp utility knife very carefully cut away approximately 1 of the tube at both headers...