Commissioning Check List
Please tick boxes when each procedure is completed
Ensure that the serial number has been recorded on the
front of the manual for future use
Visual Inspection of appliance and flue ensure that all
internal components are fitted correctly (these may
have shifted in transit)
Ensure the door seals are in good condition and that
the glass is secured correctly in the door (do not over
tighten the glass as this will prohibit its expansion and
could cause the glass to crack)
Test on flue including satisfactory smoke test: Record
flue draught reading
Spillage test preformed in accordance with available
guidance
Check socket joints and seals on the flue and
appliance
Instruct user on correct fuels and fuel storage
Ensure the customer is aware that fumes may be given
off during the first firings as the paint cures
Instruct user on essential maintenance in particular
annual maintenance of appliance and flue
Hand over user instructions & demonstrate operation
and all controls to the user
Ensure that a Notice plate has been completed and
fixed in position
Ensure that an approved Carbon Monoxide alarm has
been fitted