background image

36

ZX1.5-R 

I N S T R U C T I O N   M A N U E L

Note on safety at work

Operation by trained specialists familiar 
with the particular switchgear only.

6.1 Commissioning
6.1.1 Preparatory work

In preparation for commissioning, the following 
work is to be performed prior to connection 
with the high voltage power supply:

•  

Connect the supply and control voltage 

and check the correct polarity

•  

Check mechanical and electrical interlocks for 

compliance with the specified conditions

•  

Perform a functional test on the protective 

devices (observe DIN VDE 0141)

•  

Check the general condition of the 

switchgear and external conditions for 
detrimental factors of any kind

•  

Display the instructions for handling SF6 in 

the switchroom. The handling specifications 
for SF

6

 also apply accordingly to nitrogen (N2)

•  

Display the ABB instruction manual on the 

handling of insulating gas and behaviour 
during faults in the switchroom 

•  

Instruct the local operators on the 

fundamental details of operating the 
switchgear in normal service

•  

Check the readiness for operation and the 

switching condition of the upstream and 
downstream electrical equipment

•  

Perform further checks where necessary on 

the following equipment from the areas 
adjacent to the switchgear
-  Power cables
-  Control wiring
-  Supply voltage and its polarity
-  Remote controls
-  External earth with connection to main 

earthing bar (3.1)

-  Switchroom equipment
-  Switchroom condition

6.1.2 Initial start-up

•  

Comply with all relevant safety regulations

•  

Ensure that the switchgear circuit-breakers 

are in the OFF position

•  

Close the disconnector for the relevant 

busbar system

•  

Cancel any existing short-circuiting and earthing 

connections in the critical switching area

•  

Check that corresponding conductor sections 

are in line where relevant with several 
incoming feeders and switchgear sections

•  

Energise the switchgear step by step

•  

Check measurements and functions 

dependant on high voltage

•  

Look out for irregularities of any kind

6.2 Switching operations
6.2.1 Circuit breaker
(Figures 3/7, 6/1, 6/2, 6/4)

The circuit breaker is fitted with a charging 
motor. Charging of the spring energy storage 
mechanism takes place automatically.

Opening and closing the circuit breaker

•  

Closing and opening are effected by 

operation of the devices fitted

•  

ON-OFF switching operations may only be 

performed with the control cabinet door closed

Opening the control cabinet door 
constitutes intervention in the interlock 
system. Opening of the control cabinet 
door can constitute intervention in the 
interlock system (see sections 3.8 to 3.10).

•  

Observe the position indicator

Manual charging of the stored-energy spring

1. On failure of the charging motor,the charging 

process can be performed or completed by 
hand:

•  

Open control cabinet door (4.3)

•  

Insert charging lever (6.3) into recess (1.40) 

and pump for approx. 25 strokes until the 
charged condition is displayed

When the charged condition is reached, the 
charging mecha nism automatically 
disengages and further strokes of the 
charging lever have no effect.

Key to the charging condition displays:

2. If the control voltage fails with the circuit 

breaker closed, it is possible to open it using 
the mechanical OFF push button (1.35).

Emergency operation of the mechanical ON 
pushbutton for the circuit breaker operating 
mechanism on failure of auxiliary voltage 
(figure 6/6b)

Caution: Interlocks are cancelled during 
this operation. Only open or close circuits 
with the circuit breaker! The three position 
switch must be in a limit position !

Release the fastening screws in the circuit breaker 
cover and remove the cover. Use a suitable tool 
to press the pin in the blocking magnet (2.41) to 
the right and simultaneously move the slide 
(2.42) to close the circuit breaker.

Note

On failure of the control voltage, there is 
no maloper ation protection for the circuit 
breaker and three-postion switch during 
emergeny manual operation

6.2.2 Three-position switch
(Figures 3/7, 6/1, 6/3 and 6/5)

•  

The three position switch  (2.1)  is fitted with 

a motor-operated mechanism. Opening and 
closing are effected by selection on the 
multifunction protection and switchbay 
control unit or by means of the devices fitted

•  

Routine opening/closing operations 

may only be performed with the control 
cabinet door closed. Opening of the 
control cabinet door can constitute 
intervention in the interlock system (see 
sections 3.8 to 3.10)

•  

Observe the switch position indication on the 

electrical position indicators

•  

Sensors 2.28 to 2.31 or microswitches 2.37 to 

2.40 on the three position switch operating 
mechanism detect the switch positions
-  Disconnector (-Q1) ON and OFF
-  Earthing switch (-Q5) ON and OFF

Emergency manual operation

In place of motorised operation, the switching 
process can also be initiated and completed 
manually.

Caution!
Intervention in the interlock concept is 
possible by opening the control cabinet door.

•  

Switch the three-position switch on or off 

manually

This requires the following actions:
-  Open the control cabinet door
-  Switch the circuit breaker off
-  With the " mechanical interlock between 

circuit breaker and three position switch " 
option, opening flap (2.22) on the three 
position switch operating mechanism 
activates a mechanical interlock between 
the two devices

Note

The flap (2.22) can only be opened when the 
circuit breaker is OFF.

•  

Prior to emergency manual operation, switch 

off the mcbs for the circuit breaker release 
circuit and for the operating mech anism of 
the position switch

•  

Insert the crank (6.1) in the hollow shaft (2.26)

•  

A cam fitted at the crank prevent in cooperation 

with a bolt which is routed at the operation 
mechanism to run over the middle position

•  

Three-position switch operation

If the three-position switch is in the central 
position (i.e. disconnector and earthing switch 
OFF), the disconnector can be closed with 
approx. 24 clockwise turns, and the earthing 
switch with approx. 24 anti-clockwise turns. 
If the " earthing switch ON " position is to be 
reached from the " disconnector ON " position, 
or vice versa, the crank is to be removed in the 
self-inhibiting central position (disconnector 
and earthing switch OFF) and refitted. When 
the  crank is refitted, the further switching 
operation is automatically enabled.

Note

Always perform every switching operation right 
up to the stop in the relevant limit position.

•  

Close flap (2.22) again

If the hand crank is withdrawn in an intermediate 
position, the flap cannot be closed.

This intermediate position can be seen on the 
one hand by the lack of a mechanical limit 
position indication for the three position switch 
and also by the electrical displays on the front 
door.

The limit positions are only correctly indicated 
when the switch is in a limit position, i.e. when 
the contacts have full current carrying capacity. 
The flap (2.22) can then be closed and the circuit 
breaker switched on.

When the circuit breaker is open, the flap can 
also be opened in an intermediate position 

and the hand crank fitted to permit manual 
completion of a switching operation.

The specific data for the relevant order are 
also to be observed.

Note

When the flap (2.22) is open, the circuit breaker 
is mechanically and electrically blocked in the 
OFF position

•  

Close the control cabinet door

Emergency manual operation of the three position 
switch in a riser panel on failure of auxiliary voltage 
(optional mechanical interlock) (figure 6/6a)

Caution: Interlocks are cancelled during 
this operation. Only open or close circuits 
with the circuit breaker! The three position 
switch must be in a limit position! 

The flap (2.22) is released and access to the 
emergency manual operation shaft provided by 
pulling the interlock pin on the blocking 
magnet (2.41).

6.2.3 Undervoltage release

Undervoltage releases may be fitted as an 
option. In order to prevent the circuit breaker 
being opened by the undervoltage release on 
power failure with tee-off earthing, a tie wire is 
provided.

6.3 Observation of the display and monitoring 

facilities

6.3.1 Gas monitoring
(Figures 6/1, 6/7)

All high voltage compartments in the switchgear 
must have a sufficient insulating gas pressure 
during operation. The minimum funcional level 
for insulation is listed in section 2.1. This is  
monitored by sensors (1.8) and (2.3).

If the gas pressure falls below the alarm level for 
insulation, a LED on the multifunction protection 
and switchbay control unit signals that the gas 
should be topped up. With conventional  panel 
control, the issue of the signal is optional and 
dependent on the individual project.

Note

If a panel is isolated for a relatively long period 
(several weeks), mcb (F116) for the auxiliary 
voltage supply to the must remain on. Only in 
this way monitoring of  the  insulating gas is 
ensured. With conventional panel control, the 
details in the order documents are to be observed.

Details on the gas system of the ZX1.5-R switchgear  
can be found in instruction manual.

6.3.2 Electrical/mechanical display/monitoring

During operation of the switchgear, observe all 
visible operating data and condition displays in 
the secondary system and watch out for 
irregularities of any kind, including the external 
conditions of the switchgear.

6.4 Test procedures
6.4.1 Testing for the off-circuit condition

The panels are fitted with the low impedance, 
capacitive voltage indicator system for testing 
of the off-circuit condition.

For details, see VDE 0682 Part 415, or IEC 61243 
Part 5.

Note

Only display units which comply with the 
IEC or VDE standards and the technical 
design of the indicator system in the relevant 
switchgear may be used!

Note

The measuring sockets must on no account 
be short-circuited, except during voltage 
testing of the system (e.g. with power 
frequency withstand voltage or impulse 
withstand voltage)!

Testing for the off-circuit condition is performed 
with a plug in display unit at corresponding pairs 
of measuring sockets (1.6) and optional at (4.5) 
(Front side).

Use of the display unit

•  

Perform a functional test on the display unit 

immediately before and after use, e.g. with 
interface tester. The display must be clearly 
visible

•  

The presence of operating voltage is indicated 

by a signal

•  

Observe the individual operating instructions 

for the display unit for the relevant switchgear

Interface testing

•  

Perform interface testing as a functional test 

on all coupling components, e.g. with interface 
tester

•  

The interface test is a repeat test to IEC 61243 

Part 5 or VDE 0682 Part 415

6.4.2 Testing for the in-line condition

Testing for the in-line condition, e.g. when there 
is more than one incoming feeder, can be performed 
with a suitable line comparator at  measuring 
sockets (1.6 and 4.5 respectively) on the capacitive 
voltage indication system.

Test procedure:

•  

Only use line comparators which comply with 

the IEC or VDE specifications and the technical 

design of the display system in the relevant 
switchgear

•  

Perform a functional test on the equipment 

at the start of testing

•  

Do not exceed the maximum permissible length 

of measuring leads per line

•  

Connect the measuring leads precisely assigned 

to the corresponding main conductor sections

•  

Always follow the details in the operating 

instructions for the line comparator

6.4.3 High voltage tests

(Figures 3/7, 6/1, 6/6)

The test plugs available for high voltage tests, 
shown in figure 6/6, are suitable for the following 
applications up to and including 27.5 kV rated 
voltage.

Optional test cables can be used for high voltage 
tests.

On account of the sensor technology used and 
the multifunction protection and switchbay 
control unit, the test voltage must not exceed 
the following levels:

•  

Insulation testing of the switchgear at the 

relevant power frequency withstand voltage 
(The voltage value in site shall not exceed 
80% of the following value) 

-  

27.5 kV switchgear: 95 kV

Performance of voltage test plugs

•  

Isolate the switchgear area in accordance 

with the safety rules according to VDE 0105/EN 
50110 and secure it to prevent reconnection

•  

Verify the off-circuit condition with a suitable 

hand-held display unit at measuring sockets 
(1.6) or (4.5) on the capacitive voltage indicator 
system

•  

Unscrew surge arresters where fitted and close 

off the exposed sockets with insulating cable 
dummy plugs

•  

Close off empty cable sockets with insulating 

cable dummy plugs

•  

Check the test plug to ensure that the surface 

is clean and dry, and clean it if necessary

•  

Grease the insulating part of the test plugs in 

accordance with the instructions

•  

Unscrew cable dummy plug (1.5) in the relevant 

test socket (1.4) and remove it

•  

Connect an earthing lead to the test plug, 

following the instructions on safety at work 
in figure 6/7

•  

Insert the test plug into the prepared test socket 

and screw it tight

Notes

•  

Only fit the test plugs for voltage tests for 

the duration of those tests

•  

Short-circuit the measuring sockets (1.6) 

or (4.5) in the panels concerned for the 
duration of the testing process at test 
voltages up to rated power frequency 
withstand voltage

•  

For performance of cable tests, in the switching 

condition" tee-off " disconnected and earthed, 
earthing of  the cable has to be cancelled by 
opening the circuit breaker. This is accom 
plished by using the mechanical OFF button to 
open the circuit-breaker (see also Section 3.10)

6.4.4 Protection tests by primary current injection

(Figures 6/1 and 6/7)

In testing of protection functions by primary 
current injection, the primary current is conducted 
into the panel via the test sockets. Current test 
plugs, which are to be fitted as described below, 
are inserted in the test sockets.

•  

Observe the manufacturers instructions for 

current test plugs

•  

Isolate the relevant area of the switchgear in 

accordance with the safety regulations of 
VDE 0105/EN 50110 and secure it to prevent 
reconnection

•  

Check the off-circuit condition with a suitable 

(hand-held) indicator unit at the measuring 
sockets (1.6 or 4.5) of the capacitive voltage 
indicator system

•  

Check the test plugs to verify that the surface 

is clean and dry, and clean them if necessary

•  

Unscrew and remove the cable blanking plug 

(1.5) in the relevant test socket (1.4)

•  

Insert the test plugs into the empty test sockets 

and screw them tight

•  

Assemble the test apparatus in accordance with 

the directions from the protection test equipment 
manufacturer and perform the protection test

•  

As soon at the test is complete, remove the 

current testing plug and replace it with an 
insulating blanking plug

Note

Voltage may only be applied to the OFF 
release coil of the circuit breaker (shunt 
release OFF) for a period of 1000 ms. If this 
period is exceeded, the coil will be burn out. 
For this reason, the protection testing system 
must be shut down by the OFF release 
disconnected.

Caution!

If the circuit breaker is to be included in 
the test, it must be taken into account 
that earthing via the circuit-breaker is 
cancelled when the breaker is opened !
To prevent this, the release coil is to be 
disconnected prior to testing.

6.4.5 Maintenance earthing

•  

Earthing of the busbar with the bus tie/riser, 

as described in section 3.10

•  

Earthing with an earthing and short-circuiting set

Handling during earthing with an earthing and 
short-circuiting set:

(Figures 6/1 and 6/7)
The plugs shown in figure 6/7 in conjunction with 
corresponding short-circuiting and earthing cable 
sets are to be used for maintenance earthing. 
The short-circuit withstand capability of the 
cable set must correspond to the conditions of the 
switch-gear installation.

Caution!

Observe the notes in Section 3.8 on the interlock 
dependencies for all work with earthing and 
short-circuiting sets!

•  

Isolate the switchgear area in accordance with 

the safety rules of VDE 0105 and secure it to 
prevent reconnection

•  

Verify the off-circuit condition with a 

suitable (hand- held) display unit at 
measuring sockets (1.6) or (4.5) on the 
capacitive voltage indicator system

•  

Unscrew surge arresters where fitted and 

close off the exposed sockets with insulating 
cable dummy plugs

•  

Close off empty cable sockets with insulating 

cable dummy plugs

•  

Check the test plugs to ensure that the surface 

is clean and dry, and clean them if necessary

•  

Carefully screw the short-circuiting and earthing 

cable set to the test plug

•  

Connect the common earthing connector of the 

cable set to the earthing terminal of the panel

•  

Unscrew cable dummy plugs (1.5) in the relevant 

test socket (1.4) and remove it

•  

Insert the test plugs into the prepared test 

sockets and screw them tight

6.5 Safety note on operation of the voltage 

transformers

The screws marked in figure 5/13 establish the 
earthing connections to the relevant cable 
terminals in the terminal box shown (illustration 
shows condition as delivered).

The wiring and in particular the earthing of the 
secondary terminals is to be implemented in 
accordance with the circuit diagrams!

Releasing the earthing screw on the "N" 
terminal leads to potentially lethal high 
voltage at the terminal during operation 
of the voltage transformers!

Releasing earthing screw "N" is only 
permissible when the voltage transformers 
are off-circuit on the primary side (for test 
purposes)!

The relevant switchgear section is to be isolated 
and earthed before the isolating system for the 
voltage transformers is operated! (The 5 VDE 
safety rules are to be observed.)

Always use original earthing screws!

6.6 Application of the X-ray regulations

One of the physical properties of vacuum 
insulation is the possibility of X-ray emissions 
when the contact gap is open. The specified type 
test performed by the Physikalisch-Technische 
Bundesanstalt (PTB) in Brunswick in Germany 
demonstrates that the local dosage output of 1 

μSv/h at a distance of 10 cm

 from the touchable 

surface is not exceeded.

The results are as follows:

•  

The use of the vacuum interrupters at rated 

voltage is completely safe

•  

Application of the rated power frequency 

withstand voltage specified for the switching 
device by VDE 0670 and IEC 62271 or a DC voltage 
of 48 kV or 70 kV during cable tests is also safe

•  

Higher voltages than the rated power frequency 

withstand voltage specified in DIN VDE or IEC 
standards or the DC voltage must not be 
applied

•  

Fulfillment of the above requirement with the 

vacuum interrupter in the open position is 
dependent on maintenance of the specified 
distance between the contacts (which is 
automatically ensured with correct mechanism 
function and force transmis sion)

Circuit breaker compartment
Circuit breaker
Circuit breaker operating mechanism
Pressure relief disk, above
Test socket
Blind plug
Measuring sockets for capacitive voltage 
indicator
Plug-in cable socket
Pressure sensor for circuit breaker 
compartment
Pressure relief duct (optional)
Absorber (optional)
Drying agent bag, circuit breaker     
compartment 
Bushing circuit breaker compartment / 
busbar compartment
Filling valve for circuit breaker compartment
Protection cover for current transformer 
terminal board
Cover for metering cables
Handling bracket (to be removed after 
handling)
Edge protection
Socket head screw M 8x25
Hexagon nut M 8
Dished washer8
Centre of gravity
ON-release shaft
OFF-release shaft
Cam
Mechanical interlock circuit breakerr/ 
three-position switch
Lever
Clamping piece
Clamping screw
Tee-off conductor, bus-coupler
Tee-off conductor bus-riser
Front plate
On push button
OFF push button
Operating cycle counter
Mechanical position indicator
Rating plate
Charging condition indicator
Recess for charging lever (6.3)
Terminal board for current transformer
Auxiliary switch

Busbar compartment
Three-position switch
Three-position switch operating       
mechanism
Pressure sensor for busbar compartment
Busbar
Plug-in busbar connector
Tee-off conductor, metering panel

1.0
1.1
1.2
1.3
1.4
1.5
1.6

1.7
1.8

1.9
1.10
1.11

1.12

1.14
1.16

1.17
1.18

1.19
1.20
1.21
1.22
1.23
1.24
1.25
1.26
1.27

1.28
1.29
1.30
1.31
1.32
1.33
1.34
1.35
1.36
1.37
1.38
1.39
1.40
1.41
1.42

2.0
2.1
2.2

2.3
2.4
2.5
2.6

Support
Plug-in socket for voltage transformer
Isolating system for voltage transformer
Tee-off conductor
Pressure relief disk for busbar
compartment
Drying agent bag, busbar compartment
Busbar socket
Insulating part
O-Ring
Socket head bolt M 10x50
Guide pin
Hexagon nut M 10
Dished washer 10
Socket head bolt M 10
Bus connector
Flap
Bore for padlock
Central gas connector for busbar
compartment
Drive motor for three-position switch
Hollow shaft (emergency manual
operation shaft)
Mechanical switch position indicator
Sensor, disconnector ON
Sensor, disconnector OFF
Sensor, earthing switch ON
Sensor, earthing switch OFF
Bore for padlock
Contact ring
Manual drive for isolating device
Tie wire
Auxiliary switch
Microswitch, disconnector on
Microswitch, disconnector off
Microswitch, earthing switch off  
Microswitch, earthing switch on
Blocking magnet
Slide (mechanical operation circuit 
breaker ON)

Cable termination compartment
Main earthing bar
Panel / panel connecting link
Cable mounting (optional)
Cable plug
Pressure relief flap, optional
Lower pressure relief duct
High voltage cable
Parallel connector PB50,
GCE 0909125P0100
Floor plate splitted
Reducer ring
Cable mounting
Supporting section, at earth potential
Rear panel compartment
Supporting section, at earth potential

Pressure relief flap, optional
Socket for fully insulated bar
Fully insulated bar
Venti lator

Control cabinet
Central unit of the Bay Control and
Protection Unit
HMI of the Bay Control and Protection Unit
Control cabinet door
Door-lock
Measuring sockets for capacitive
voltage indicator, optional
Light-emitting diode (LED)
LC-Display of the Bay Control and 
Protection Unit
Closing lever
Double bit lock or security lock

Measuring facilities
Current transformer
Plug-in voltage transformer
Block-current transformer
Terminal board for current transformer

Accessories
Hand crank
Double bit key
Charging lever for emergency manual 
operation
Test plug for high voltage tests, optional
Test plug for current tests, optional

2.7
2.8
2.9
2.10
2.11

2.12
2.13
2.14
2.15
2.16
2.17
2.18
2.19
2.20
2.21
2.22
2.23
2.24

2.25
2.26

2.27
2.28
2.29
2.30
2.31
2.32
2.33
2.34
2.35
2.36
2.37
2.38
2.39
2.40
2.41
2.42

3.0
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8

3.9
3.10
3.11
3.12
3.13
3.14

3.15
3.16
3.17
3.18

4.0
4.1

4.2
4.3
4.4
4.5

4.6
4.7

4.8
4.9

5.0
5.1
5.2
5.3
5.4

6.0
6.1
6.2
6.3

6.4
6.5

Foundation frame
Longitudinal bracket, (this one for panel 
width 600 mm)
Longitudinal bracket, internal (this one 
for panel width 600 mm) 
Transverse bracket, left (this one for 
panel depth 1300 mm)
Transverse bracket, right (this one for 
panel depth 1300 mm)
Fixing angle bracket
Connecting link
Transverse bracket for two panel frame, 
(this one for panel depth 1300 mm)
Connecting angle
Screwed connection for foundation frame
Socket head bolt M 8x25
Socket head bolt M 10x25
Socket head bolt M 8x25
Socket head bolt M 8x25, frame height 40 mm
Socket head bolt M 8 x 35, frame height 
50 mm
Partition plate
Dished washer8
Dished washer 10
Washer8
Nut M10
Fixing dowel

7.0
7.1

7.2

7.3

7.4

7.5
7.6
7.7

7.8
7.9
7.10
7.11
7.12
7.13
7.14

7.15
7.20
7.21
7.22
7.23
7.30

Summary of Contents for ZX1.5-R

Page 1: ... Safety and reliability 20 footprint saving Easy operation Complete solution INSTRUCTION MANUEL ZX1 5 R Gas insulated medium voltage for railway application ...

Page 2: ......

Page 3: ...Summary 2 Technical data 3 Design and function of the switchgear system and its equipment 4 Despatch and storage 5 Erection of the switchgear at site 6 Commissioning operation 7 Maintenance disposal 8 Table of equipment designations used ...

Page 4: ...handling Paragraphs in this manual are marked in accordance with their significance The markings mean the following Hazard warning meaning in this manual that death or serious injury and considerable damage may occur if the actions described are not performed Important note meaning in this manual that injury and damage may occur if the actions described are not performed Attention is drawn to furt...

Page 5: ...llation and operation in particular Power installations exceeding AC 1kV DIN VDE 0101 Operation of electrical installations VDE 0105 Earthing systems for special power installations with rated voltages above 1 kV DIN VDE 0141 The accident prevention regulations issued by the appropriate professional bodies The safety guidelines for production materials The order related details provided by the swi...

Page 6: ...r insulation Pae Rated filling level for insulation Pre Motor and release data Charging motor Closing coil Opening coil Rated supply voltage DC Degree of protection IEC 60529 DIN VDE 0470 1 High voltage live part Control cabinet Ambient temperature Maximum temperature Maximum temperature of 24 hours mean Minimum value Opearting Altitude Dimensions Height for transport Depth 9 10 11 Width Height of...

Page 7: ...eak withstand current Rated short time current 4 s Motor data Motor power max 1 Motor running times max 1 Centre position to busbar Centre position to earth Rated supply voltage DC 2 line to earth line to line Across the isolating distance line to earth line to line Across the isolating distance kV kV kV A kA kA W s s V 27 5 2x27 5 95 140 118 200 325 220 2500 80 31 5 180 18 18 60 110 220 1 At rate...

Page 8: ...sure relief duct above F Pressure relief duct for busbar compartment G Pressure relief duct with absorber I Pressure relief chimney lateral E Pressure relief duct above F Pressure relief duct for busbar compartment G Pressure relief duct with absorber A Circuit breaker compartment B Busbar compartment C Cable termination compartment partitioned D Control cabinet Incoming feeder panel up to 4 cable...

Page 9: ...a pressure relief duct F see page 9 from the busbar compartments to a metering panel or sectionalizerpanel If the installation does not contain a metering panel or sectionalizer panel anoutgoing feeder panel can be used for pressure relief The panels can have optionally integrated pressure relief ducts with the opportunity for Conducting out of the switchroom in a manner suitable for the building ...

Page 10: ...rd the plasma gases are discharged through the lower pressure relief duct 3 6 to the side pressure relief chimney I refer to page 9 and into the upper pressure relief duct 1 9 Optionally in systems with pressure relief to the rear discharge is effected centrally via the pressure relief duct 3 6 into a sectionalizer panel busbar riser panel or metering panel There flap 3 15 opens Cable termination ...

Page 11: ...reaker compartment 1 0 The circuit breaker operating mechanism 1 2 is located outside the gas compartment and is therefore easily accessible It is connected to the breaker poles by a gas tight bushing Functions of the vacuum circuit breaker 1 1 Opening and closing on rated currents Short circuit breaking operations Earthing function in conjunction with three position switch 2 1 The earthing functi...

Page 12: ... the ZX1 5 R has microswitches on the operating mechanism base plate figure 6 2 for detection of the position of the three position switch 2 1 These are used to start and stop the relevant drive motor disconnector or earthing switch These microswitches are used to activate and deactivate the relevant mechanism motor function disconnector or earthing switch 5 pole sets of auxiliary switches are ava...

Page 13: ...ded to protect the operators and the switchgear itself Note If the operating mechanism for the three position switch fail during a switching operation when the switch is in an intermediate position the electrical interlock between the VD4 X R circuit breaker and the UX2TE R three position switch established by the REO 517 is effective The VD4 X R circuitbreaker could however be closed mechanically...

Page 14: ...ionalizers risers permit earthing ofa busbar section without additional equipment 3 10 1 Electrical earthing of a busbar section using the sectionalizer riser Operating sequence Circuit breaker in the sectionalizer panel OFF All disconnectors in the busbar section to be earthed OFF apart from the disconnector Q11 or Q12 between the busbar section to be earthed and the sectionalizer breaker Secure ...

Page 15: ...to the conductors in the connection area is possible without releasing the cable connection Access is effected via the test sockets 1 4 Surge arresters must be removed during voltage tests The empty sockets must be closed with insulating blanking plugs during testing Voltage transformers must be isolated from the test circuit prior to testing Voltage tests Close and insulate free cable sockets wit...

Page 16: ...oor Figure 3 4 Panel top pressure relief disk on the circuit breaker compartment Shown before installation of a pressure relief duct or plasma Figure 3 5 Panel top pressure relief disk on the circuit breaker compartment Shown with plasma deflector assembled 1 3 Figure 3 3 Figure 3 4 Figure 3 5 1 15 ...

Page 17: ...in busbar connector 3 0 Cable termination compartment 3 1 Main earthing bar 3 4 Cable plug 3 6 Lower pressure relief duct 3 7 High voltage cable 4 0 Control cabinet 4 3 Control cabinet door 4 4 Door lock 5 3 Block current transformer Insulating gas Q0 Circuit breaker Q1 Tee off disconnector Q5 Tee off earthing switch T1 Current transformer C1 Capacitive voltage divider Insulating gas Q0 Circuit br...

Page 18: ...ion Unit 4 2 HMI of the Bay Control and Protection Unit 4 3 Control cabinet door 4 4 Door lock 4 5 Measuring sockets for capacitive voltage indicator optional Insulating gas Q0 Circuit breaker Q1 Tee off disconnector Q5 Tee off earthing switch T1 Current transformer C1 Capacitive voltage divider C2 Capacitive voltage divider optional Insulating gas Q0 Circuit breaker Q1 Tee off disconnector Q5 Tee...

Page 19: ...tor Q5 Tee off earthing switch T1 Current transformer T5 Voltage transformer C1 Capacitive voltage divider ZX1 5 R Figure 3 9 Outgoing feeder panel double pole 2000 A with 4 cables per pole and voltage transformer Isolating system 2 9 is only to be operated when the feeder is off circuit Alwaysperform switching operations up to the limit positions and lock the isolating system Figure 3 10 Outgoing...

Page 20: ...e off earthing switch T1 Current transformer T5 Voltage transformer C1 Capacitive voltage divider C2 Capacitive voltage divider optional ZX1 5 R Figure 3 11 Outgoing feeder panel double pole 2500 A with 4 cables per pole and busbar voltage transformer shown with pressure relief duct Figure 3 11 ...

Page 21: ...ENT Channel Channel Channel Channel Channel Channel Channel Channel L2 L2 L2 3 12 Circuit diagram for panel with conventional metrology Transformation rating accoring to order documentation X 80 Figure 3 12 Conventional current and voltage transformers Figure 3 12 ...

Page 22: ...nsport Figure 4 1 Note Do not walk on the tops of the panels pressure relief system The transport units are normally individual panels Always handle the panel in the upright position Take account of the weight of the transport units when selecting the handling equipment Due to the high centre of gravity of the panel blocks there is a risk that the transport units may tip over Take all precautions ...

Page 23: ...rdance with VDE 0670 Part 1000 IEC 62271 1 Room temperature not falling below 25 No other injurious environmental influences Store the panels upright Do not stack panels Panels with basic packaging Open the packaging at least partially Panels without packaging Loosely cover with protective sheeting Sufficient air circulation must be preserved Check regularly for any condensation 2 Panels with seaw...

Page 24: ...so as to achieve a precise rated tightening torque Remove any dirt from the surfaces in general and from insulating material surfaces Observe the cleaning instructions in Section 7 2 When handling SF6 avoid any escape of gas into the switchroom Ventilate well if leakage occurs 5 2 2 Perform the following work to prepare silicone insulating parts for assembly Inspect the sillicone insulating parts ...

Page 25: ...nels Figures 5 1 to 5 6 Note Do not walk on the top of the panels rupture point for pressure relief system 5 4 1 Preparatory work Before joining up the panels check the gas pressure in each gas compartment witha temperature compensated pressure gauge GCE0905091P101 The indication must be in the green area of the scale on the measuring instrument If there is any deviation from the specified pressur...

Page 26: ...to the foundation frame Figure 5 18b Dismantle connecting link 3 2 for the main earthing bar 3 1 in the cable compartment and lead it through to the adjacent panel Bolt the connecting link to the main earthing bar with bolts 2 20 and one dished washer at each of the bolt head and nut ends Check the bolted connection between main earthing bar 3 1 and the connecting link 3 2 in the previously erecte...

Page 27: ...tchgear assembly Figure 5 2a Switchgear assembly see figures 5 1 to 5 4 for details Multifunction protection and switch bay control unit not shown completely Figure 5 2b Switchgear assembly insulating part On assembly of the busbar the conical surface A is to be evenly lubricated with assembly paste No areas must be left unlubricated Figure 5 2a Figure 5 1 Figure 5 2b ...

Page 28: ...st be checked 1250 A 1 contact ring 1250 A 2 contact rings L1 L3 Protective caps removed L2 Insulating part 2 14 and bus connector 2 21 fitted Figure 5 3 Switchgear assembly Earthing bar connection Figure 5 4 Switchgear assembly Panel panel connection Figure 5 5 Busbar connection Figure 5 6 Assembly of the busbar connection shown for 1250 A Figure 5 3 Figure 5 5 Figure 5 6 Figure 5 4 ...

Page 29: ...ltage transformer Figure 5 8 Insertion area for voltage transformer top view Figure 5 9 Insertion area during assembly Figure 5 10 Insertion area fiual position Figure 5 7 Figure 5 8 Figure 5 9 Figure 5 10 Note Don t step on the bersting plate If necessary protect during assembly with sheet plate ...

Page 30: ...gure 5 13 Earthing screws for the voltage transformer terminals as delivered here for voltage transformer with 2 secondary terminals Figure 5 14 Plug connector for single core XLPE cableK Cable earthing conductor to be connected to switchgear earth Refer to the mounting instruction of the supplier Figure 5 15 Cable termination compartment single core cable panel side wall cut out Figure 5 11 Figur...

Page 31: ...e Front Openning of foundation frame Layout of foundation frame Channel Steel 1 When the optional 500mm deep low voltage compartment is used these dimensions increase by 100 mm Tolerance conditions for laying of the frame as follows Evenness tolerance 1 mm per meter Straightness tolerance max 1mm per metre but max 2mm for the entire length of the frame ...

Page 32: ...forcement plate below the transformers and screwed to the hexagon pins evenly across the diagonal up to the mechanical stop max tightening torque 15 Nm Where possible wipe off any surplus grease which emerges 32 ZX1 5 R INSTRUCTION MANUEL Connect the wiring for the secondary connections and the earthing of the voltage transformer in accordance with the circuit diagrams Check that all terminal scre...

Page 33: ...amage to the paintwork touching up with a suitable paint if necessary see Section 7 3 3 Properly refit any cladding and covers of operating mechanisms cable ducts etc Removed during the erection work Remove all tools and other foreign bodies from the switchgear Check the general condition of the switchgear Check that the areas adjacent to the switchgear are in the proper condition ...

Page 34: ...tart up Comply with all relevant safety regulations Ensure that the switchgear circuit breakers are in the OFF position Close the disconnector for the relevant busbar system Cancel any existing short circuiting and earthing connections in the critical switching area Check that corresponding conductor sections are in line where relevant with several incoming feeders and switchgear sections Energise...

Page 35: ...control cabinet door Switch the three position switch on or off manually This requires the following actions Open the control cabinet door Switch the circuit breaker off With the mechanical interlock between circuit breaker and three position switch option opening flap 2 22 on the three position switch operating mechanism activates a mechanical interlock between the two devices Note The flap 2 22 ...

Page 36: ... details in the order documents are to be observed Details on the gas system of the ZX1 5 R switchgear can be found in instruction manual 6 3 2 Electrical mechanical display monitoring During operation of the switchgear observe all visible operating data and condition displays in the secondary system and watch out for irregularities of any kind including the external conditions of the switchgear 6...

Page 37: ... the duration of those tests Short circuit the measuring sockets 1 6 or 4 5 in the panels concerned for the duration of the testing process at test voltages up to rated power frequency withstand voltage For performance of cable tests in the switching condition tee off disconnected and earthed earthing of the cable has to be cancelled by opening the circuit breaker This is accom plished by using th...

Page 38: ...h the earthing connections to the relevant cable terminals in the terminal box shown illustration shows condition as delivered The wiring and in particular the earthing of the secondary terminals is to be implemented in accordance with the circuit diagrams Releasing the earthing screw on the N terminal leads to potentially lethal high voltage at the terminal during operation of the voltage transfo...

Page 39: ...Hollow shaft emergency manual operation shaft 2 27 Mechanical switch position indicator 2 3 Pressure sensor for busbar compartment 2 36 Auxiliary switch 2 37 Microswitch disconnector on 2 38 Microswitch disconnector off 2 39 Microswitch earthing switch off 2 40 Microswitch earthing switch on 1 14 Filling valve for circuit breaker compartment 1 2 Circuit breaker operating mechanism 1 33 Front plate...

Page 40: ...t test plugs the following must be ensured The safety regulations of VDE 0105 are followed e g the section of the switchgear concerned De energised Is secured to prevent reconnection The off circuit conditions has been verified and It is earthed The occurrence of high voltage by secondary injection from the voltage transformers must be avoided Before and during fitting and removal of the test plug...

Page 41: ...ng cycles of the circuit breaker and 1 000 operating cycles of the three position switch Attention is also drawn to instruction manual 1YHA000118 In exceptional operating conditions including adverse climatic conditions and or particularly adverse environments including heavy contamination and aggressive atmosphere inspection at shorter intervals may be required Inspection is first and foremost to...

Page 42: ...rection is necessary tie wire 2 35 is to be adjusted Release clamping screw 1 30 on clamping piece 1 29 Align flap 2 22 in such a way that the two bores 2 23 are in alignment Fasten tie wire 2 35 with clamping screw 1 30 in such away that the abovementioned distance of 2 1 mm is achieved The tie wire must not be tensioned 7 3 3 Touch up of surfaces Sheet steel parts painted Remove rust e g with a ...

Page 43: ...s Isoflex Topas NB 52 Assembly paste for insulating part cast resin plug connections Silicone paste for greasing of o rings Cleaning agent for busbar insulating parts busbar sockets and cable sockets Cable cleanser MAB Paintwork Paint in standard colour RAL 7035 1 kg box Spray tin Coupling piece with hose connection for gas connector optional Part no Orderref GCE0990253P0103 GCEA901004P0102 GCE099...

Page 44: ... standard Density sensor for circuit breaker compartment Density sensor for busbar compartment Sensor to detect switch position circuit breaker OFF Sensor to detect switch position circuit breaker ON Sensor to detect the charging condition of the stored energy spring for the circuit breaker Sensor to detect switch position three position switch earthing switch OFF Sensor to detect switch position ...

Page 45: ...7 1 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 32 1 33 1 34 1 35 1 36 1 37 1 38 1 39 1 40 1 41 1 42 2 0 2 1 2 2 2 3 2 4 2 5 2 6 Support Plug in socket for voltage transformer Isolating system for voltage transformer Tee off conductor Pressure relief disk for busbar compartment Drying agent bag busbar compartment Busbar socket Insulating part O Ring Socket head bolt M 10x...

Page 46: ...s optional Test plug for current tests optional 3 15 3 16 3 17 3 18 4 0 4 1 4 2 4 3 4 4 4 5 4 6 4 7 4 8 4 9 5 0 5 1 5 2 5 3 5 4 6 0 6 1 6 2 6 3 6 4 6 5 Foundation frame Longitudinal bracket this one for panel width 600 mm Longitudinal bracket internal this one for panel width 600 mm Transverse bracket left this one for panel depth 1300 mm Transverse bracket right this one for panel depth 1300 mm F...

Page 47: ...stant that enables customers to connect to the broadest range of electrification solutions in one place Easy to find what you need by search Get all information about our products applications selection guides installation manuals service certificates and engineering tools etc Saving documents locally updating automatically Receive your expected messages Online customer service You can use ABB Con...

Page 48: ...rict Xiamen Fujian 361101 Tel 0592 602 6033 Fax 0592 603 0505 ABB China Customer Service Hot Line TEL 800 820 9696 400 820 9696 mail cn ep hotline abb com www abb com 1YHA000326_EN REV A 06 2021 XM LDZ All rights reserved Specifications subject to change without notice ...

Reviews: