Danger:
Hazardous voltage
•
Do not commission the EVSE. Only a service engineer of the
manufacturer is qualified to commission the EVSE.
Procedure
1. Tell the owner that the EVSE is ready for commissioning.
2. Make sure that the site complies with these requirements:
•
The EVSE is installed.
•
AC input power is available from the grid provider.
•
The AC input cable has the minimum required cross-section. For the
specifications, refer to section
•
You are present during the commissioning, for assistance and to switch on
the power on the distribution board.
•
Internet access is available, through 3G/4G or Ethernet connection.
•
An EV must be available with a compatible connection.
•
The site operator or owner is available to receive instructions from the
service engineer of the manufacturer.
3. Make sure that these requirements are met:
•
You are present during the commissioning, for assistance and to energize
the power to the EVSE on the power distribution board.
•
An EV is available with a compatible connection.
•
The site operator or owner is available to receive instructions from the
service engineer of the manufacturer.
4. Make sure that this data is available:
•
Contact data of the contact person on site.
•
Address of the EVSE.
•
Site name.
•
Exact location of the EVSE: longitude and latitude. If there are more EVSEs
at one location, make sure that the coordinates are slightly different (at least
0.0001 degree). This way the EVSEs are not at the same location on the map.
•
Specification of the external fuse at the power distribution board.
•
Date that the installation is done.
•
Special remarks, for example to decline the authorization for the service
engineer of the manufacturer to take photos.
•
Photo of the surroundings of the EVSE.