4 4 3 Connecting with UPS and Other Battery Pack
Follow the below installation diagram to connect the UPS with other battery pack(s)
(Second battery pack) by cable.
NOTE
REMOVE THE BATTERY CONNECTOR COVER BEFORE CONNECTING WITH
UPS AND OTHER BATTERY PACK.
UPS
First battery pack
Second battery pack
—
4.4.3-1
—
5 Battery Installation
If your battery pack is not installed with batteries, please follow the proper procedure
to put batteries inside of the unit
NOTE
MAKE SURE THAT THE BATTERY PACK IS DISCONNECTED FROM THE UPS
BEFORE PERFORMING THE FOLLOWING SEQUENCE OF OPERATIONS.
WARNING
• THE EQUIPMENT SHOULD BE INSTALLED BY SERVICE PERSONNEL
• WHEN INSTALLING THE BATTERIES, USE THE SAME NUMBER AND
TYPE OF BATTERIES SHOWN IN THE BATTERY LABEL
• DO NOT OPEN OR MUTILATE THE BATTERY OR BATTERIES,
RELEASED ELECTROLYTE IS HARMFUL TO THE SKIN AND EYES
• A BATTERY CAN PRESENT A RISK OF ELECTRIC SHOCK AND HIGH
SHORT CIRCUIT CURRENT. THE FOLLOWING PRECAUTION SHOULD
BE OBSERVED WHEN WORKING ON BATTERIES
A) Remove watches, rings or other metal objects.
B) Use tools with insulated handles
Step 1: Remove the topcover as below diagram.
—
5-1
Step 2: Remove the battery fixing plates from the bottom case as below diagram.
—
5-2
—
5-1
Step 1
—
5-2
Step 2