Installation
Mounting and dismounting
You can mount and unmount the MTQ22-FBP.0 onto a 35 mm standard mounting rail without tools.
Mounting Dismounting
—
03 Mounting and dismounting the MTQ22-FBP.0 on a 35 mm standard mounting rail.
Electrical Installation
General
Arrange the communication cables as far away from the motor cables as possible. Avoid parallel runs. Use bushings at cable
entries.
Ethernet connection
The network cable is connected to the RJ45 connectors on the MTQ22-FBP.0 module. Standard CAT5 UTP, FTP or STP cables
can be used. The shield of the RJ45 cable is connected to the shield of connector X6.
Power Supply connection
The MTQ22-FBP.0 has to be supplied with 24 V DC on the terminals X6. Using the shield connection is optional.
FBP Device connection
FBP devices (e.g. UMC100) can be connected point to point using the ready made cable CDP17.
This option is recommended in non withdraw-able installations (e.g. using a mounting plate for the installation).
In case the FBP device is mounted within a withdraw-able unit (drawer) all the needed cables and auxiliaries are
available as well as shown in detail in the figure below.
The distance between the MTQ22-FBP.0 and the FBP device must not exceed 3 meters.
The communication cables between MTQ22-FBP.0 and UMC100 must not run in parallel to the motor cables.