13
7.
Install platforms & accessories
A. H
ook on the platforms on the lifting frame.
B.
Install
all the ramps.
Fig. 7-A
Fig. 7-B-1
Fig. 7-B-2
3.4. Preparation for Starting up
3.4.1 The
locks are automatic and will
engage
when
in operation
.
3.4.2 The hydraulic oil should be ISO-32.or 46
3.4.3 Have a certificate electrician establish
240V/50Hz, single
phase power supply
.
A
n
(RC
D
)
protection will need to be installed by an electrician
3.4.4 Air Evacuation. There may
be a
little air in the hose or cylinder during installation.
Operat
e
the
hoist
up and down ieveral times without load
until the air is bled
.
3.4.5 Raise the
hoist
about
600mm
high and then lower it. Repeat this process two or three
times, and then top off the hydraulic oil reservoir again, if necessary. This assures that
hydraulic oil is distributed everywhere in the system that it needs to be.
Only top off the reservoir with the
hoist
at the “ground” position.
Summary of Contents for AutoLift AL-167262
Page 7: ... 7 Fig 01 ...
Page 9: ...2 4Circuit Diagram 9 ...
Page 10: ......
Page 14: ......
Page 19: ... 17 6 Parts Drawing ...
Page 20: ... 18 ...
Page 21: ... 19 ...