Note
Use this installation diagram when you:
-
install the water connections (see 8.4)
-
install the condensate drain (see 8.5)
-
install the gas connection (see 8.6)
-
fill the water heater (see 8.9.1)
-
drain the water heater (see 8.10.2)
n
8.4
Water connections
8.4.1
Cold water connection
Install the cold water connection:
1.
Install an approved stop valve (4), as required by the applicable regulations (on page
4).
2.
Install an approved pressure reducing valve (1) to prevent that the pressure in the
cold water supply pipe exceeds the maximum working pressure of the tank, 8 bar.
Refer to the Technical details.
3.
Install a non-return valve (5).
4.
Install an expansion valve (15).
5.
Connect the overflow connection of the expansion valve, to an open waste water
pipe.
6.
Install an expansion vessel (16).
8.4.2
Hot water connection
Note
Insulate long hot water pipes to prevent unnecessary energy loss.
Install the hot water connection:
1.
Install a stop valve (11) in the hot water outlet pipe for service reasons.
2.
If applicable, install a temperature gauge (12).
3.
Install a T&P valve (3).
8.4.3
Circulation connection
Install a circulation pump when an immediate flow of hot water at draw-off points is
required. This improves comfort and reduces water wastage.
Note
Use the special connection for the circulation pipe on the water heater for a more
efficient use of the water heater.
Note
Make sure that the pump has the correct capacity for the length and resistance of the
circulation system.
Install a circulation pump:
1.
Install a circulation pump (6).
2.
Install a non-return valve (5) after the circulation pump to make sure that the
direction of circulation is guaranteed.
3.
Install a stop valve (4) before the circulation pump.
4.
Install a stop valve (4) after the non-return valve.
5.
Connect the circulation pipe.
n
n
40
Installation, Maintenance and Service part
Summary of Contents for Innovo IR 12-160
Page 6: ...6 ...
Page 13: ...User part 0312266_INNOVO_UKUK_V5 1 2022 07 12 13 ...
Page 14: ...14 ...
Page 16: ...16 User part ...
Page 18: ...18 User part ...
Page 24: ...24 User part ...
Page 27: ...Installation Maintenance and Service part 0312266_INNOVO_UKUK_V5 1 2022 07 12 27 ...
Page 28: ...28 User part ...
Page 36: ...36 Installation Maintenance and Service part ...
Page 56: ...56 Installation Maintenance and Service part ...
Page 58: ...58 Installation Maintenance and Service part ...
Page 70: ...70 Installation Maintenance and Service part ...
Page 83: ...0312266_INNOVO_UKUK_V5 1 2022 07 12 83 ...
Page 87: ...13 4 Electrical wiring diagram 0312266_INNOVO_UKUK_V5 1 2022 07 12 87 ...
Page 89: ...13 5 Declaration of conformity 0312266_INNOVO_UKUK_V5 1 2022 07 12 89 ...
Page 90: ......
Page 91: ......
Page 94: ...92 Installation Maintenance and Service part ...